2 data center projects in San Marcos City
Who decides here: the City Council of San Marcos City votes on zoning. The Hays County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In San Marcos City
Highlander SM One data center (Francis Harris Lane, San Marcos)
San Marcos, Hays County
200 acres
🕒 Feb 18, 2026: San Marcos City Council voted 5-2 to deny a land use change for the data center.
ProposedSabey data center campus (Centerpoint Road, San Marcos)
San Marcos, Hays County
786 acres
🕒 June 3, 2025: San Marcos City Council approved starting negotiations on a development agreement with S…
Reported in the news, not confirmed yet
Nearby (within 15 miles)
Edged Austin data center campus (Maxwell)
Unincorporated Caldwell County, Caldwell County
330 acres
🕒 Oct 14, 2026: A state air permit for the 'Caldwell Power Generation Plant: Edged Energy Campus Caldwel…
Reported in the news, not confirmed yet
Being builtabout 8 miles awayCloudBurst 1.2 GW data center campus (between San Marcos and New Braunfels)
Unincorporated Guadalupe County, Guadalupe County
706 acres
🕒 April 21, 2026: Guadalupe County Commissioners Court approved a $500 million tax break and a development…
Proposedabout 10 miles awayTract Caldwell Valley Technology Park (near Uhland)
Unincorporated Caldwell County, Caldwell County
2,973 acres
🕒 Oct 22, 2026: By Oct. 22, after watchdog groups reported these permits, the state had suspended at lea…
Being builtabout 11 miles awayPrime Data Centers AUS01 and AUS02 (Bob White Road, near Lockhart)
Unincorporated Caldwell County, Caldwell County
206 acres
🕒 May 2026: Prime filed state plans for AUS01 and AUS02; construction set to start June 2026.
Reported in the news, not confirmed yet
Local votes and rules
🚫 Ban
San Marcos City Council voted 4-3 to define data centers in its zoning code and not allow them in any zoning district. It is the first Texas city to ban data centers. A state senator has said he will challenge the ban under state law.
✋ Turned down
After a nine-hour meeting, San Marcos City Council voted 5-2 to reject a land use change for a $1.5 billion data center on about 200 acres on Francis Harris Lane, next to the Hays Energy power plant. The developer was Highlander SM One LLC. The developer may refile within six months.
What you can do
- Get told first.
We'll email you if anything changes in San Marcos City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in San Marcos City: Pedernales Electric Co-op, Inc. (co-op (owned by its members)) or Bluebonnet Electric Co-op, Inc. (co-op (owned by its members)) or City of San Marcos (run by the town).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.
🙋 Open tasks here
- Will the developer refile after six months (about August 2026)?
- Will the developer try to build outside city control instead?
- Has a development agreement been signed or voted on?
- Is the land inside San Marcos city limits or its ETJ?
- How much power and water would it use?