Highlander SM One data center (Francis Harris Lane, San Marcos)
Also called: Highlander SM One LLC
Highlander SM One LLC, from Fort Worth, wanted to build a $1.5 billion data center on 200 acres on Francis Harris Lane between San Marcos and New Braunfels, next to the Hays Energy power plant. After hundreds of residents came out, mostly against it, the City Council voted 5-2 at 2:14 a.m. to deny the land use change. An earlier zoning change also failed in summer 2025.
What happens next?
Where things stand: Stopped or cancelled San Marcos City Council denied the land use change 5-2 on Feb. 18, 2026. The developer could refile after six months.
❓ 2 open questions about it: see below.
📣 See work going on anyway? Tell us
Last checked Oct 6, 2026.
🕒 Latest update (Feb 18, 2026): San Marcos City Council voted 5-2 to deny a land use change for the data center.
What we know
- 📍 WhereFrancis Harris Lane, next to the Hays Energy power plant, San Marcos, Hays County
- 🏢 CompanyHighlander SM One LLC
- 🌳 Size200 acres
- 💵 Cost$1.5 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Will the developer refile after six months (about August 2026)? 🙋 I'll find out ·
- Will the developer try to build outside city control instead? 🙋 I'll find out ·
What happened so far
- July 2025City Council failed to pass a zoning change for the data center (it needed a supermajority).
- Feb 18, 2026San Marcos City Council voted 5-2 to deny a land use change for the data center.
Local votes and rules
🚫 Ban
San Marcos City Council voted 4-3 to define data centers in its zoning code and not allow them in any zoning district. It is the first Texas city to ban data centers. A state senator has said he will challenge the ban under state law.
✋ Turned down
After a nine-hour meeting, San Marcos City Council voted 5-2 to reject a land use change for a $1.5 billion data center on about 200 acres on Francis Harris Lane, next to the Hays Energy power plant. The developer was Highlander SM One LLC. The developer may refile within six months.
Drag the slider to compare the land before and now.
Where this comes from
- San Marcos City Council blocks proposed data center · KUT · Feb 18, 2026