ProposedBig (AI-size): 786 acres

Sabey data center campus (Centerpoint Road, San Marcos)

Also called: Carson Select San Marcos

Sabey Data Centers is exploring a data center campus on land southwest of South Old Bastrop Highway and Centerpoint Road in San Marcos. The site is about 786 acres and would include a Pedernales Electric Cooperative substation. In June 2025 the City Council voted only to start talks; the mayor said it was not a final approval.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of San Marcos City.

Where things stand: Proposed City Council agreed in June 2025 only to start talks on a development agreement.

❓ 3 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (June 3, 2025): San Marcos City Council approved starting negotiations on a development agreement with Sabey.

What we know

  • 📍 WhereSouthwest of South Old Bastrop Highway and Centerpoint Road, San Marcos, Hays County
  • 🏢 CompanySabey Data Centers
  • 🌳 Size786 acres
  • 🔌 Where the power comes fromA planned Pedernales Electric Cooperative substation

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Has a development agreement been signed or voted on? 🙋 I'll find out ·
  • Is the land inside San Marcos city limits or its ETJ? 🙋 I'll find out ·
  • How much power and water would it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • June 3, 2025
      San Marcos City Council approved starting negotiations on a development agreement with Sabey.

    Local votes and rules

    🚫 Ban

    San Marcos City Council voted 4-3 to define data centers in its zoning code and not allow them in any zoning district. It is the first Texas city to ban data centers. A state senator has said he will challenge the ban under state law.

    June 16, 2026

    ✋ Turned down

    After a nine-hour meeting, San Marcos City Council voted 5-2 to reject a land use change for a $1.5 billion data center on about 200 acres on Francis Harris Lane, next to the Hays Energy power plant. The developer was Highlander SM One LLC. The developer may refile within six months.

    Feb 18, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Sabey looks to develop data center campus outside Austin, Texas · DatacenterDynamics · June 10, 2025
    2. Texas data centers map and list · Cleanview (tracker) · Oct 2026