Proposed

Tract Caldwell Valley Technology Park (near Uhland)

Also called: Caldwell Valley Technology Park, Tract Uhland

Tract, a Colorado company that prepares land for data centers, owns almost 3,000 acres along FM 2720 near Uhland, northwest of Lockhart. It says the land can support up to 4 gigawatts of data centers. Bluebonnet Electric Cooperative and LCRA are planning an on-site substation. Other companies, such as PowerHouse, plan to build on parts of the park.

โœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Land ready for data center builders; first 250-360 MW of grid power planned for 2028.

๐Ÿ•’ Latest update (Jan 2026): Tract added 1,458 acres, bringing the park to almost 3,000 acres and up to 4 gigawatts.

What we know

  • ๐Ÿ“ WhereAlong FM 2720 near Uhland, northwest of Lockhart, Unincorporated Caldwell County, Caldwell County
  • ๐Ÿข CompanyTract
  • ๐ŸŒณ Size2,973 acres
  • โšก Power it needs4,000 megawatts (about as much as 3,200,000 homes)
  • ๐Ÿ”Œ Where the power comes fromGrid power from Bluebonnet Electric Cooperative and LCRA through a planned on-site substation that could grow to 1.6 gigawatts; first 250 MW contracted for early 2028.

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Oct 2024
    Tract first filed plans with the Uhland City Council for land along FM 2720.
  • May 2025
    Tract bought a 1,515-acre site for a data center 'megasite'; Gov. Abbott praised the project.
  • Jan 2026
    Tract added 1,458 acres, bringing the park to almost 3,000 acres and up to 4 gigawatts.

Local votes and rules

๐Ÿ“Œ Other

Caldwell County commissioners voted to put on hold all property tax breaks (Chapter 312 abatements) for large data centers. This came after months of complaints that projects were moving ahead with little public information, and after the county judge disclosed a land deal tied to another data center plan. The county had approved two such tax breaks earlier in 2026.

Aug 20, 2026

๐Ÿ“Œ Other

Caldwell County commissioners unanimously passed Resolution 29-2026. It opposes data centers that use open-loop water cooling or other heavy drinking-water use in dry areas, and any data center without safeguards. It asks the Legislature to give counties more power, since Texas counties cannot zone land.

May 14, 2026

๐Ÿค Agreement with the company

Caldwell County commissioners approved a property tax break (Chapter 312 abatement) with EDC Austin LLC for a data center to be run by Edged. It is planned on about 330 acres off State Highway 142 near the LCRA Timmerman power plant in the Maxwell area, with up to $7.3 billion in total investment.

March 26, 2026
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Tract expands Austin data center park to 3,000 acres ยท DatacenterDynamics ยท Jan 2026
  2. Data center 'megasite' is coming to Lockhart as similar facilities strain Texas' water, energy supply ยท KUT ยท May 16, 2025
  3. PowerHouse Plans Austin Suburb Data Center But Seeks To Skirt City Control ยท Bisnow ยท May 5, 2026