ProposedBig (AI-size): 4,000 megawatts

Tract Caldwell Valley Technology Park (near Uhland)

Also called: Caldwell Valley Technology Park, Tract Uhland

Tract, a Colorado company that prepares land for data centers, owns almost 3,000 acres along FM 2720 near Uhland, northwest of Lockhart. It says the land can support up to 4 gigawatts of data centers. Bluebonnet Electric Cooperative and LCRA are planning an on-site substation. Other companies, such as PowerHouse, plan to build on parts of the park.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Caldwell County Commissioners Court (for land outside city and town limits).

Where things stand: Proposed Land ready for data center builders; first 250-360 MW of grid power planned for 2028.

❓ 5 open questions about it: see below.

Last checked Oct 26, 2026.

🕒 Latest update (Oct 22, 2026): By Oct. 22, after watchdog groups reported these permits, the state had suspended at least 17 data center stormwater and wastewater permits and shut its automatic online permit system. Reports did not list which sites were suspended.

What we know

  • 📍 Where727 Farmers Road, Maxwell (address on the state stormwater permit; the park covers almost 3,000 acres along FM 2720), Unincorporated Caldwell County, Caldwell County
  • 🏢 CompanyTract
  • 🌳 Size2,973 acres
  • ⚡ Power it needs4,000 megawatts (about as much as 3,200,000 homes)
  • 🔌 Where the power comes fromGrid power from Bluebonnet Electric Cooperative and LCRA through a planned on-site substation that could grow to 1.6 gigawatts; first 250 MW contracted for early 2028.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which companies will build data centers on the park, and when? 🙋 I'll find out ·
  • How much water will the data centers use, and from where? 🙋 I'll find out ·
  • Is any part of the land inside Uhland's city limits or its ETJ? 🙋 I'll find out ·
  • Will new high-voltage power lines be built? 🙋 I'll find out ·
  • Was this site's state stormwater permit one of the at least 17 data center permits the state (TCEQ) suspended in October 2026? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 26, 2026: We checked the state stormwater permit address (727 Farmers Road, Maxwell) with the Census geocoder and moved the map pin there.

    What happened so far

    • Oct 2024
      Tract first filed plans with the Uhland City Council for land along FM 2720.
    • May 2025
      Tract bought a 1,515-acre site for a data center 'megasite'; Gov. Abbott praised the project.
    • Jan 2026
      Tract added 1,458 acres, bringing the park to almost 3,000 acres and up to 4 gigawatts.
    • Sept 22, 2026
      The state environmental agency (TCEQ) issued a construction stormwater permit for 'Caldwell Valley Technology Park' at 727 Farmers Road, Maxwell. This allows land clearing and grading. It came one day after Gov. Abbott told the agency to halt data center permits.
    • Oct 22, 2026
      By Oct. 22, after watchdog groups reported these permits, the state had suspended at least 17 data center stormwater and wastewater permits and shut its automatic online permit system. Reports did not list which sites were suspended.

    Local votes and rules

    📌 Other

    Caldwell County commissioners voted to put on hold all property tax breaks (Chapter 312 abatements) for large data centers. This came after months of complaints that projects were moving ahead with little public information, and after the county judge disclosed a land deal tied to another data center plan. The county had approved two such tax breaks earlier in 2026.

    Aug 20, 2026

    📌 Other

    Caldwell County commissioners unanimously passed Resolution 29-2026. It opposes data centers that use open-loop water cooling or other heavy drinking-water use in dry areas, and any data center without safeguards. It asks the Legislature to give counties more power, since Texas counties cannot zone land.

    May 14, 2026

    🤝 Agreement with the company

    Caldwell County commissioners approved a property tax break (Chapter 312 abatement) with EDC Austin LLC for a data center to be run by Edged. It is planned on about 330 acres off State Highway 142 near the LCRA Timmerman power plant in the Maxwell area, with up to $7.3 billion in total investment.

    March 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Tract expands Austin data center park to 3,000 acres · DatacenterDynamics · Jan 2026
    2. Data center 'megasite' is coming to Lockhart as similar facilities strain Texas' water, energy supply · KUT · May 16, 2025
    3. PowerHouse Plans Austin Suburb Data Center But Seeks To Skirt City Control · Bisnow · May 5, 2026
    4. Texas data centers map and list · Cleanview (tracker) · Oct 2026
    5. Summary: Data Center Permits Issued by TCEQ After 9/21/2026 · Public Citizen (summary of TCEQ records) · Oct 19, 2026
    6. Texas continued permitting data centers after Abbott's pause, report finds · Inside Climate News via KUT · Oct 20, 2026
    7. Texas Suspends Data Center Permits Following Watchdog Report · Industry Insider Texas (GovTech) · Oct 23, 2026