Approved, not built yetBig (AI-size): 330 acres

Edged Austin data center campus (Maxwell)

Also called: Edged Austin, Edged Energy Campus

Edged plans a data center campus on about 330 acres at 11255 Highway 142 in Maxwell, near LCRA's Timmerman gas power plant. The first building would be 869,685 square feet and cost about $2.8 billion; the full campus could reach more than 2 million square feet and $7.3 billion. Caldwell County approved a tax break.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Caldwell County Commissioners Court (for land outside city and town limits).

Where things stand: Approved, not built yet County approved a tax break; state filing lists construction from June 2026 to June 2028.

❓ 4 open questions about it: see below.

Last checked Oct 26, 2026.

🕒 Latest update (Oct 14, 2026): A state air permit for the 'Caldwell Power Generation Plant: Edged Energy Campus Caldwell County' in Martindale finished its first engineer review at TCEQ. It has not been issued.

What we know

  • 📍 Where11255 Highway 142, Maxwell (near LCRA Timmerman power plant), Unincorporated Caldwell County, Caldwell County
  • 🏢 CompanyEdged
  • 🏛️ Owned byEndeavour
  • 🌳 Size330 acres
  • 🔌 Where the power comes fromNext to LCRA's Timmerman natural gas power plant; exact power supply not stated.
  • 💵 Cost$7.3 billion
  • 💸 Tax breaksCaldwell County approved a tax break (terms not reported).

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • What are the terms of the county tax break? 🙋 I'll find out ·
  • How much power will it use, and from where? 🙋 I'll find out ·
  • How much water will it use? 🙋 I'll find out ·
  • Will Edged build its own gas power plant at the Caldwell County campus, and how big would it be? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • 2025
      An application for the project was first filed, without Edged's name.
    • 2026
      Caldwell County approved a tax break for the project.
    • May 2026
      Edged filed state plans for the first building; construction set for June 2026 to June 2028.
    • Oct 14, 2026
      A state air permit for the 'Caldwell Power Generation Plant: Edged Energy Campus Caldwell County' in Martindale finished its first engineer review at TCEQ. It has not been issued.

    Local votes and rules

    📌 Other

    Caldwell County commissioners voted to put on hold all property tax breaks (Chapter 312 abatements) for large data centers. This came after months of complaints that projects were moving ahead with little public information, and after the county judge disclosed a land deal tied to another data center plan. The county had approved two such tax breaks earlier in 2026.

    Aug 20, 2026

    📌 Other

    Caldwell County commissioners unanimously passed Resolution 29-2026. It opposes data centers that use open-loop water cooling or other heavy drinking-water use in dry areas, and any data center without safeguards. It asks the Legislature to give counties more power, since Texas counties cannot zone land.

    May 14, 2026

    🤝 Agreement with the company

    Caldwell County commissioners approved a property tax break (Chapter 312 abatement) with EDC Austin LLC for a data center to be run by Edged. It is planned on about 330 acres off State Highway 142 near the LCRA Timmerman power plant in the Maxwell area, with up to $7.3 billion in total investment.

    March 26, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Edged files to develop 2 million sq ft data center campus outside Austin, Texas · DatacenterDynamics · May 13, 2026
    2. Texas data centers map and list · Cleanview (tracker) · Oct 2026
    3. Summary: Data Center Permits Issued by TCEQ After 9/21/2026 · Public Citizen (summary of TCEQ records) · Oct 19, 2026

    See something wrong? Tell us and we'll fix it.