7 data center projects in San Antonio City
Who decides here: the City Council of San Antonio City votes on zoning. The Bexar County may review big projects too.
In San Antonio City
COPT Potranco data center shell building (San Antonio)
San Antonio, Bexar County
for unknown (Amazon reported as possible)
π March 2026: COPT filed state plans for a $25 million data center shell building.
Reported in the news, not confirmed yet
Being builtVantage data center site, TX21 and TX22 (Westover Hills, San Antonio)
San Antonio, Bexar County
31 acres
π Oct 2025: Vantage filed state plans for TX22 (214,525 sq ft, $272 million), construction Oct. 2025β¦
Being builtMicrosoft data centers SAT14, SAT15, SAT16 (Westover Hills, San Antonio)
San Antonio, Bexar County
for Microsoft
π March 2024: Microsoft filed state plans for SAT16, a 245,000-square-foot, $215 million building at 3β¦
ProposedAmazon 'Bitter Blue' data center (Donop Road, San Antonio)
San Antonio, Bexar County
for Amazon Web Services
π March 2026: Amazon Data Services filed state plans for the Bitter Blue data center.
Reported in the news, not confirmed yet
Built & runningStream Data Centers San Antonio III campus (West Military Drive)
San Antonio, Bexar County
135 acres
π June 26, 2024: Stream broke ground on its third San Antonio campus.
Reported in the news, not confirmed yet
ProposedTract 'Applewhite Technology Park' (south San Antonio)
San Antonio, Bexar County
339 acres
Reported in the news, not confirmed yet
ProposedBlack Mountain Power site (State Highway 16 and Lone Star Pass, south San Antonio)
San Antonio, Bexar County
432 acres
π Jan 2026: Black Mountain Power LLC bought 432 acres at SH 16 and Lone Star Pass.
Reported in the news, not confirmed yet
Local votes and rules
π Data center rules
San Antonio is drafting development code changes for data centers. The draft would keep data centers 500 feet from homes, schools, hospitals, nursing homes and day cares, allow them only in industrial and commercial areas, and ban them downtown. The mayor proposed noise limits under 50 dBA by day and 45 dBA at night. A council vote was planned for October 15, 2026.
π Other
Three San Antonio council members asked for a pause on new data centers. At an August 25, 2026 meeting, most of the council instead backed city staff's plan to change the development code to limit where and how data centers are built. State law requires a three-month process before a city can pause building permits.
What you can do
- Get told first.
We'll email you if anything changes in San Antonio City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in San Antonio City: Karnes Electric Co-op Inc. (co-op (owned by its members)) or Guadalupe Valley Electric Co-op Inc. (co-op (owned by its members)) or Bandera Electric Co-op, Inc. (co-op (owned by its members)) or Pedernales Electric Co-op, Inc. (co-op (owned by its members)) or City of San Antonio (run by the town).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.
π Open tasks here
- Is TX21 running yet?
- How many megawatts will the site use?
- Will it use on-site gas power like TX12?
- How much power and water do the Westover Hills buildings use?
- How many diesel backup generators are on site?
- How much power and water will it use?
- Will a new substation or power line be needed?
- Who is the tenant?
- How much power will it use?
- How many buildings are running now?
- Who is the tenant?
- How much water does it use?
- Which data center company will build here?
- Is all the land inside San Antonio city limits?
- Will this site become a data center, and when?
- Will it have its own power plant?