Being built

Microsoft data centers SAT14, SAT15, SAT16 (Westover Hills, San Antonio)

Also called: SAT14, SAT15, SAT16, SAT17

Microsoft keeps adding data center buildings in San Antonio's Westover Hills area. It filed plans for SAT16, a $215 million building on Westover Link, and is building a multi-building campus called SAT14 on Wiseman Boulevard. Microsoft has invested over $1.2 billion in local data centers since 2015.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of San Antonio City.

Where things stand: Being built Several Microsoft buildings opened or are being built here since 2023; trackers list SAT16 and SAT17 as planned.

❓ 2 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (March 2024): Microsoft filed state plans for SAT16, a 245,000-square-foot, $215 million building at 3555 Westover Link.

What we know

  • 📍 Where3555 Westover Link and 3545 Wiseman Blvd, Westover Hills, San Antonio, Bexar County
  • 🏢 CompanyMicrosoft
  • 👤 Built forMicrosoft
  • 💵 Cost$415 million

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much power and water do the Westover Hills buildings use? 🙋 I'll find out ·
  • How many diesel backup generators are on site? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 2023
      Microsoft was clearing land for a large new data center on Westover Link and building SAT14 on Wiseman Boulevard.
    • March 2024
      Microsoft filed state plans for SAT16, a 245,000-square-foot, $215 million building at 3555 Westover Link.

    Local votes and rules

    📜 Data center rules

    San Antonio's schedule for its data center development code changes: a City Council briefing on Oct. 14 (2 p.m.), the Zoning Commission on Oct. 20 (1 p.m., 1901 S. Alamo St.), and a City Council vote on Oct. 29, 2026 (9 a.m., 114 W. Commerce St.). The draft would limit data centers to industrial and commercial areas, keep them 500 feet from homes, schools and hospitals, and ban them over the Edwards Aquifer Recharge Zone.

    Oct 29, 2026

    📜 Data center rules

    San Antonio City Council voted 9-2 to change its development code for data centers. Every new data center now needs its own permit from City Council (a specific use authorization), so the public can speak on each one. Data centers are allowed only in heavy commercial and industrial zones and not over the Edwards Aquifer recharge zone. There is no fixed distance from homes; council will set limits case by case. Council also added a required distance from the UNESCO World Heritage missions. Stricter (1,000-ft) and looser (by-right with 350 ft) options both failed.

    Oct 29, 2026

    📜 Data center rules

    San Antonio is drafting development code changes for data centers. The draft would keep data centers 500 feet from homes, schools, hospitals, nursing homes and day cares, allow them only in industrial and commercial areas, and ban them downtown. The mayor proposed noise limits under 50 dBA by day and 45 dBA at night. A council vote was planned for October 15, 2026.

    Aug 26, 2026

    📌 Other

    Three San Antonio council members asked for a pause on new data centers. At an August 25, 2026 meeting, most of the council instead backed city staff's plan to change the development code to limit where and how data centers are built. State law requires a three-month process before a city can pause building permits.

    Aug 25, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Microsoft plans $482m data center in San Antonio, Texas · DatacenterDynamics · July 30, 2024
    2. Denver data center company buys 89 acres on far West Side · San Antonio Report · Aug 31, 2023
    3. Texas data centers map and list · Cleanview (tracker) · Oct 2026

    See something wrong? Tell us and we'll fix it.