ProposedBig (AI-size): 720 megawatts

Tract 'Applewhite Technology Park' (south San Antonio)

Also called: Applewhite Technology Park

Tract markets 339 acres of industrially zoned land on San Antonio's south side, near Toyota and Texas A&M San Antonio, for data centers. A tracker lists it at 720 megawatts.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of San Antonio City.

Where things stand: Proposed Land marketed for data centers; no builder announced.

❓ 2 open questions about it: see below.

Last checked Oct 6, 2026.

What we know

  • 📍 WhereSouth side of San Antonio, near Toyota and Texas A&M San Antonio, San Antonio, Bexar County
  • 🏢 CompanyTract
  • 🌳 Size339 acres
  • ⚡ Power it needs720 megawatts (about as much as 576,000 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which data center company will build here? 🙋 I'll find out ·
  • Is all the land inside San Antonio city limits? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    Local votes and rules

    📜 Data center rules

    San Antonio's schedule for its data center development code changes: a City Council briefing on Oct. 14 (2 p.m.), the Zoning Commission on Oct. 20 (1 p.m., 1901 S. Alamo St.), and a City Council vote on Oct. 29, 2026 (9 a.m., 114 W. Commerce St.). The draft would limit data centers to industrial and commercial areas, keep them 500 feet from homes, schools and hospitals, and ban them over the Edwards Aquifer Recharge Zone.

    Oct 29, 2026

    📜 Data center rules

    San Antonio City Council voted 9-2 to change its development code for data centers. Every new data center now needs its own permit from City Council (a specific use authorization), so the public can speak on each one. Data centers are allowed only in heavy commercial and industrial zones and not over the Edwards Aquifer recharge zone. There is no fixed distance from homes; council will set limits case by case. Council also added a required distance from the UNESCO World Heritage missions. Stricter (1,000-ft) and looser (by-right with 350 ft) options both failed.

    Oct 29, 2026

    📜 Data center rules

    San Antonio is drafting development code changes for data centers. The draft would keep data centers 500 feet from homes, schools, hospitals, nursing homes and day cares, allow them only in industrial and commercial areas, and ban them downtown. The mayor proposed noise limits under 50 dBA by day and 45 dBA at night. A council vote was planned for October 15, 2026.

    Aug 26, 2026

    📌 Other

    Three San Antonio council members asked for a pause on new data centers. At an August 25, 2026 meeting, most of the council instead backed city staff's plan to change the development code to limit where and how data centers are built. State law requires a three-month process before a city can pause building permits.

    Aug 25, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Applewhite Technology Park · Tract (company) · 2026
    2. Applewhite Technology Park (Tract), Bexar County, TX · More Than Just Parks (tracker) · 2026

    See something wrong? Tell us and we'll fix it.