Amazon 'Bitter Blue' data center (Donop Road, San Antonio)
Also called: Bitter Blue
Amazon filed state plans for a two-story, roughly 120,000-square-foot data center called Bitter Blue at 12807 Donop Road on San Antonio's southeast side. It is estimated to cost about $65 million.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of San Antonio City.
Where things stand: Proposed State filing lists construction from Dec. 2026 to Feb. 2029.
❓ 2 open questions about it: see below.
Last checked Oct 6, 2026.
🕒 Latest update (March 2026): Amazon Data Services filed state plans for the Bitter Blue data center.
What we know
- 📍 Where12807 Donop Road, San Antonio, Bexar County
- 🏢 CompanyAmazon Data Services, Inc.
- 🏛️ Owned byAmazon
- 👤 Built forAmazon Web Services
- 💵 Cost$65 million
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How much power and water will it use? 🙋 I'll find out ·
- Will a new substation or power line be needed? 🙋 I'll find out ·
What happened so far
- March 2026Amazon Data Services filed state plans for the Bitter Blue data center.
Local votes and rules
📜 Data center rules
San Antonio's schedule for its data center development code changes: a City Council briefing on Oct. 14 (2 p.m.), the Zoning Commission on Oct. 20 (1 p.m., 1901 S. Alamo St.), and a City Council vote on Oct. 29, 2026 (9 a.m., 114 W. Commerce St.). The draft would limit data centers to industrial and commercial areas, keep them 500 feet from homes, schools and hospitals, and ban them over the Edwards Aquifer Recharge Zone.
📜 Data center rules
San Antonio City Council voted 9-2 to change its development code for data centers. Every new data center now needs its own permit from City Council (a specific use authorization), so the public can speak on each one. Data centers are allowed only in heavy commercial and industrial zones and not over the Edwards Aquifer recharge zone. There is no fixed distance from homes; council will set limits case by case. Council also added a required distance from the UNESCO World Heritage missions. Stricter (1,000-ft) and looser (by-right with 350 ft) options both failed.
📜 Data center rules
San Antonio is drafting development code changes for data centers. The draft would keep data centers 500 feet from homes, schools, hospitals, nursing homes and day cares, allow them only in industrial and commercial areas, and ban them downtown. The mayor proposed noise limits under 50 dBA by day and 45 dBA at night. A council vote was planned for October 15, 2026.
📌 Other
Three San Antonio council members asked for a pause on new data centers. At an August 25, 2026 meeting, most of the council instead backed city staff's plan to change the development code to limit where and how data centers are built. State law requires a three-month process before a city can pause building permits.
Drag the slider to compare the land before and now.
Where this comes from
- AWS files to develop data centers in San Antonio, Texas · DatacenterDynamics · March 2026
- Amazon's 'Lavender Hill' Data Fortress Riles San Antonio's West Side · Hoodline · March 31, 2026
- Texas data centers map and list · Cleanview (tracker) · Oct 2026