Vantage data center site, TX21 and TX22 (Westover Hills, San Antonio)
Also called: TX21, TX22
Vantage Data Centers bought 31 acres at State Highway 151 and Wiseman Boulevard in San Antonio's Westover Hills area in 2023, across the road from Microsoft data centers. It filed state plans for TX21, a $157 million, three-story building, and TX22, a $272 million, two-story building at 5207 Rogers Road.
Where things stand: TX21 was filed for Dec. 2023 to June 2025; TX22 ($272 million) is filed for Oct. 2025 to June 2027.
๐ Latest update (Oct 2025): Vantage filed state plans for TX22 (214,525 sq ft, $272 million), construction Oct. 2025 to June 2027.
What we know
- ๐ Where5207 Rogers Road (State Highway 151 and Wiseman Boulevard), Westover Hills, San Antonio, Bexar County
- ๐ข CompanyVantage Data Centers
- ๐ณ Size31 acres
- ๐ต Cost$429 million
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Is TX21 running yet? ๐ I'll find out
- How many megawatts will the site use? ๐ I'll find out
- Will it use on-site gas power like TX12? ๐ I'll find out
What happened so far
- Aug 9, 2023Vantage bought 31 acres at the north corner of State Highway 151 and Wiseman Boulevard.
- Nov 2023Vantage filed state plans for TX21 (360,000 sq ft, $157 million).
- Oct 2025Vantage filed state plans for TX22 (214,525 sq ft, $272 million), construction Oct. 2025 to June 2027.
Local votes and rules
๐ Data center rules
San Antonio is drafting development code changes for data centers. The draft would keep data centers 500 feet from homes, schools, hospitals, nursing homes and day cares, allow them only in industrial and commercial areas, and ban them downtown. The mayor proposed noise limits under 50 dBA by day and 45 dBA at night. A council vote was planned for October 15, 2026.
๐ Other
Three San Antonio council members asked for a pause on new data centers. At an August 25, 2026 meeting, most of the council instead backed city staff's plan to change the development code to limit where and how data centers are built. State law requires a three-month process before a city can pause building permits.
Drag the slider to compare the land before and now.
Where this comes from
- Denver data center company buys 89 acres on far West Side ยท San Antonio Report ยท Aug 31, 2023
- Vantage files to build another data center in San Antonio, Texas ยท DatacenterDynamics ยท Oct 15, 2025
- Texas data centers map and list ยท Cleanview (tracker) ยท Oct 2026