COPT Potranco data center shell building (San Antonio)
Also called: COPT Potranco
COPT, a real estate company that is a known landlord for Amazon data centers, filed state plans for a two-story, 142,000-square-foot 'core and shell' building for a future data center at 1535 NW Crossroads. News reports say Amazon may be the tenant, but this is not confirmed.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of San Antonio City.
Where things stand: Proposed State filing lists construction from Oct. 2026 to Nov. 2027; tenant not confirmed.
❓ 2 open questions about it: see below.
Last checked Oct 7, 2026.
🕒 Latest update (March 2026): COPT filed state plans for a $25 million data center shell building.
What we know
- 📍 Where1535 NW Crossroads, near Potranco Road, San Antonio, Bexar County
- 🏢 CompanyCOPT
- 👤 Built forunknown (Amazon reported as possible)
- 💵 Cost$25 million
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who is the tenant? 🙋 I'll find out ·
- How much power will it use? 🙋 I'll find out ·
🔎 What we checked
- Oct 7, 2026: We checked the site location: exact address found.
What happened so far
- March 2026COPT filed state plans for a $25 million data center shell building.
Local votes and rules
📜 Data center rules
San Antonio's schedule for its data center development code changes: a City Council briefing on Oct. 14 (2 p.m.), the Zoning Commission on Oct. 20 (1 p.m., 1901 S. Alamo St.), and a City Council vote on Oct. 29, 2026 (9 a.m., 114 W. Commerce St.). The draft would limit data centers to industrial and commercial areas, keep them 500 feet from homes, schools and hospitals, and ban them over the Edwards Aquifer Recharge Zone.
📜 Data center rules
San Antonio City Council voted 9-2 to change its development code for data centers. Every new data center now needs its own permit from City Council (a specific use authorization), so the public can speak on each one. Data centers are allowed only in heavy commercial and industrial zones and not over the Edwards Aquifer recharge zone. There is no fixed distance from homes; council will set limits case by case. Council also added a required distance from the UNESCO World Heritage missions. Stricter (1,000-ft) and looser (by-right with 350 ft) options both failed.
📜 Data center rules
San Antonio is drafting development code changes for data centers. The draft would keep data centers 500 feet from homes, schools, hospitals, nursing homes and day cares, allow them only in industrial and commercial areas, and ban them downtown. The mayor proposed noise limits under 50 dBA by day and 45 dBA at night. A council vote was planned for October 15, 2026.
📌 Other
Three San Antonio council members asked for a pause on new data centers. At an August 25, 2026 meeting, most of the council instead backed city staff's plan to change the development code to limit where and how data centers are built. State law requires a three-month process before a city can pause building permits.
Drag the slider to compare the land before and now.
Where this comes from
- AWS files to develop data centers in San Antonio, Texas · DatacenterDynamics · March 2026
- OpenStreetMap search: 1535 Northwest Crossroads, San Antonio · OpenStreetMap contributors · Oct 7, 2026
See something wrong? Tell us and we'll fix it.