1 data center project in Conewago Township
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Conewago Township votes on zoning. The York County Planning Commission usually reviews big projects too.
In Conewago Township
Nearby (within 15 miles)
Royal Manchester Golf Links data center rezoning (East Manchester Township)
East Manchester Township, York County
Proposedabout 8 miles awayFairview Crossroads data center (Fairview Township, York County)
Fairview Township, York County
π July 28, 2025: Supervisors unanimously revised zoning to allow data centers with setback and noise rules.
Proposedabout 8 miles awayBriarwood golf course data center (West Manchester Township)
West Manchester Township, York County
π Oct 2025: West Manchester Township supervisors approved the zoning change the data center needs, wβ¦
Status unclearabout 11 miles awayLondonderry Township data center (Dauphin County)
Londonderry Township, Dauphin County
π Aug 4, 2025: Public hearing on a data center overlay ordinance. The township said no data center applβ¦
Reported in the news, not confirmed yet
Proposedabout 12 miles awayWindsor Township data center (Elysian Partners)
Windsor Township, York County
π Aug 2025: A Florida real estate company urged the township to allow data centers.
Proposedabout 13 miles awayCorscale Highlands West data center (Dauphin Highlands golf course, Swatara Township / Steelton)
Swatara Township, Dauphin County
228 acres
π Sept 2026: Corscale filed a 73-page lot consolidation and final land development plan: three 409,50β¦
Conewago Township Planning Commission. We don't know yet if Rexroth Farms data center (Conewago Township, York County) is on the agenda. Call the office to check before you go.
Local votes and rules
π Data center rules
Conewago Township in York County is drafting rules that would allow data centers only in a special overlay zone, with special approval. Sites would need at least 100 acres and buildings would have to be 500 feet from homes.
π Other Β· York County
The York County Planning Commission wrote a model data center ordinance that towns can copy and change. It suggests keeping buildings 150 to 200 feet from all property lines and limiting noise at nearby homes to 60 decibels on a 24-hour weighted average.
What you can do
- Get told first.
We'll email you if anything changes in Conewago Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Conewago Township: FirstEnergy Pennsylvania (formerly Met-Ed) (company) or Adams Electric Cooperative Inc. (co-op (owned by its members)).