ProposedBig (AI-size): 541 acres

Rexroth Farms data center (Conewago Township, York County)

Also called: Elysian Partners

A Florida developer and a farm family asked to change Conewago Township's zoning to allow a data center on a 541-acre farm. Residents strongly oppose it.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Conewago Township.

Where things stand: Proposed Rexroth and Elysian Partners asked the township to change its zoning text to allow data centers as a conditional use. Supervisors held a data center workshop in June 2026; no vote on the change found.

❓ 2 open questions about it: see below.

Last checked Nov 2, 2026.

🕒 Latest update (June 2, 2026): Supervisors voted 3-0 to advertise a workshop on data centers; many residents spoke against data centers.

What we know

  • 📍 Where1465, 1670 and 1940 Bowers Bridge Road (three farm parcels), Conewago Township, York County
  • 🏢 CompanyElysian Partners and Rexroth Farms
  • 🌳 Size541 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

    What happened so far

    • Sept 22, 2025
      At the planning commission, Elysian Partners presented its proposed zoning text change to allow data centers; Rexroth said its solar option had expired and it wanted to allow uses like a data center.
    • Oct 27, 2025
      More than 100 people attended a four-hour planning commission meeting; all speakers opposed.
    • June 2, 2026
      Supervisors voted 3-0 to advertise a workshop on data centers; many residents spoke against data centers.

    Local votes and rules

    📜 Data center rules

    Conewago Township in York County is drafting rules that would allow data centers only in a special overlay zone, with special approval. Sites would need at least 100 acres and buildings would have to be 500 feet from homes.

    Sept 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. What to know about Rexroth proposal for a Conewago Twp. data center · York Dispatch (via AOL) · April 21, 2026
    2. Planning Commission (2026 meeting dates) · Conewago Township · Oct 6, 2026
    3. Board of Supervisors (2026 meeting dates) · Conewago Township · Oct 6, 2026
    4. Conewago Township Planning Commission minutes, Sept. 22, 2025 · Conewago Township · Sept 22, 2025
    5. Conewago Township Board of Supervisors minutes, June 2, 2026 · Conewago Township · June 2, 2026
    6. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
    7. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
    8. Planning Commission agenda (Rexroth data center zoning text amendment) · Conewago Township · Oct 27, 2025
    9. U.S. Census Geocoder result for 1940 Bowers Bridge Rd, Manchester, PA 17345 · U.S. Census Bureau · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.