Briarwood golf course data center (West Manchester Township)

Colorado-based Viridian Partners wants to build a data center on the Briarwood Golf Club land in West Manchester Township. Supervisors approved a zoning change for it in October 2025. The developer still needs approval of a detailed plan.

✔ ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Supervisors approved a zoning change for the project in Oct. 2025, with conditions. The developer must still bring back a detailed plan for approval.

🕒 Latest update (Oct 2025): West Manchester Township supervisors approved the zoning change the data center needs, with some conditions on how it looks.

🗓️ Public meeting: Oct 13, 2026 · 7:00 PM
West Manchester Township Planning Commission. Anyone can come and speak.
Agenda includes a discussion of noise from industrial and commercial uses; Briarwood not listed.
📍 Township Municipal Building, 380 E. Berlin Rd., York, PA 17408, and on Zoom (meeting ID 818 6730 4378, passcode 215859; no comments over Zoom). Call (717) 792-3505 before noon Oct. 9 with questions or comments, or speak in person.

What we know

  • 📍 WhereBriarwood Golf Club, West Market Street, West Manchester Township, York County
  • 🏢 CompanyViridian Partners (Colorado)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

🔎 What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

What happened so far

  • Oct 2025
    West Manchester Township supervisors approved the zoning change the data center needs, with some conditions on how it looks.
🛰️ See it from above

Drag the slider to compare the land before and now.

2018–20202021–2023
We only know the town, so this shows the town center, not the exact site. Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

📣 Report something

Where this comes from

  1. York County golf course land one step closer to being used for a data center · abc27 · Oct 2025
  2. Briarwood Data Center (West Manchester Township) · More Than Just Parks Data Center Tracker · Oct 23, 2025
  3. Public Notice - Planning Commission Meeting - October 13, 2026 · West Manchester Township · Sept 28, 2026
  4. Data centers are coming for golf courses · GOLF.com · Dec 10, 2025
  5. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
  6. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026

See something wrong? Tell us and we'll fix it.