Fairview Crossroads data center (Fairview Township, York County)
Also called: Elysian Partners
Fairview Township changed its zoning in 2025 to allow data centers as a conditional use. A developer, Fairview Crossroads LLC (linked to Elysian Partners), has proposed a 750,000-square-foot, $500 million data center near I-83.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Fairview Township.
Where things stand: Proposed Township changed zoning in July 2025 to allow data centers with limits.
❓ 2 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (July 28, 2025): Supervisors unanimously revised zoning to allow data centers with setback and noise rules.
What we know
- 📍 WhereLewisberry Road near Interstate 83 (York County parcel 27000SF0003A0, about 83 acres, owned by Fairview Crossroads LLC), Fairview Township, York County
- 🏢 CompanyFairview Crossroads LLC (Elysian Partners)
- 💵 Cost$500 million
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Has a land development plan been filed? 🙋 I'll find out ·
- How big would it be? 🙋 I'll find out ·
🔎 What we checked
- Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.
What happened so far
- July 28, 2025Supervisors unanimously revised zoning to allow data centers with setback and noise rules.
Local votes and rules
📜 Data center rules
Fairview Township in York County approved a zoning change that sets rules for data centers. Local reports say it limits them to business and industrial zones as a conditional use, with sound studies, height limits and setbacks.
Drag the slider to compare the land before and now.
Where this comes from
- Local officials are preparing for a wave of data centers in York County · York Dispatch · July 31, 2025
- Fairview Crossroads Data Center (Elysian Partners, Fairview Township) · More Than Just Parks Data Center Tracker
- 750,000 sq ft data center could be built in Fairview Township, Pennsylvania · DatacenterDynamics · 2025
- Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
- Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
- York County parcels (owner Fairview Crossroads LLC: 83.26-acre parcel 27000SF0003A0 on Lewisberry Rd plus 3 small lots) · York County via PASDA · Oct 8, 2026