Corscale Highlands West data center (Dauphin Highlands golf course, Swatara Township / Steelton)
Swatara Township, Dauphin County
228 acres
🕒 Oct 12, 2026: The golf course is set to close.
Approved, not built yetCorscale Highlands East data center (Highland Street, Swatara Township)
Swatara Township, Dauphin County
157 acres · for unknown (developer says a tenant is in mind, no signed deal)
🕒 Nov 4, 2026: Swatara Township commissioners voted 4-1 to conditionally approve Corscale's data center…
Nearby (within 15 miles)
Fairview Crossroads data center (Fairview Township, York County)
Fairview Township, York County
🕒 July 28, 2025: Supervisors unanimously revised zoning to allow data centers with setback and noise rules.
Proposedabout 6 miles awayHCI DP Land Acquisition data center (South Hanover Township quarry)
South Hanover Township, Dauphin County
250 acres
🕒 June 23, 2026: Crowd packed township building after supervisors announced the two applications.
Status unclearabout 8 miles awayLondonderry Township data center (Dauphin County)
Londonderry Township, Dauphin County
🕒 Aug 4, 2025: Public hearing on a data center overlay ordinance. The township said no data center appl…
Reported in the news, not confirmed yet
Proposedabout 11 miles awayRexroth Farms data center (Conewago Township, York County)
Conewago Township, York County
541 acres
🕒 June 2, 2026: Supervisors voted 3-0 to advertise a workshop on data centers; many residents spoke agai…
Stopped or cancelledabout 12 miles awayRoyal Manchester Golf Links data center rezoning (East Manchester Township)
East Manchester Township, York County
Proposedabout 13 miles awayPA Data Center Partners / PowerHouse data center (Monroe Township, Cumberland)
Monroe Township, Cumberland County
Reported in the news, not confirmed yet
Local votes and rules
✅ Approved
Swatara Township commissioners voted 4-1 to conditionally approve Corscale's data center plan on 157 acres off Highland Street, behind WITF. Corscale must meet 17 conditions before the final plan is signed and recorded, and it still needs state permits.
🗺️ Zoning change
Swatara Township's planning commission received a proposed zoning change that could allow another data center campus on three properties along Pennhar Drive and Rupp Hill Road. The commission had not reviewed it yet. Commissioners make the final decision.
🤝 Agreement with the company
Swatara Township commissioners voted 4-1 to approve community benefits agreements with Corscale Data Centers worth about $120.3 million for its two planned data center sites (Highlands West on the old golf course, and Highlands East). The money comes in steps as building goes ahead and would pay for police and fire buildings, roads and other needs. Residents had asked for a delay; that motion failed 4-1.
What you can do
- Get told first.
We'll email you if anything changes in Swatara Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- Where will its water and power come from?
- How much water and how many backup generators would the golf course site use?
- Corscale has given two totals for both Swatara sites ($10.5 billion in Sept. 2026 and $14.5 billion in Oct. 2026). Which is current?
- What did the Swatara Township Planning Commission recommend on the golf course data center plan at its Nov. 10, 2026 meeting, and when will commissioners vote?
- Who is the tenant that will use the data centers?
- How many megawatts of power will the site use?
- Did Swatara Township sign an agreement with the developer to keep the plans private (NDA)?
- Will new power lines be needed to serve the site?
- Corscale has given two totals for both Swatara sites ($10.5 billion in Sept. 2026 and $14.5 billion in Oct. 2026). Which is current?
- What are the 17 conditions Swatara Township attached to its Nov. 4, 2026 approval of the Highland Street data center?