USA › Pennsylvania › Dauphin County › Swatara Township

2 data center projects in Swatara Township

Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Swatara Township votes on zoning. The Dauphin County Planning Commission usually reviews big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

In Swatara Township

Nearby (within 15 miles)

Local votes and rules

✅ Approved

Swatara Township commissioners voted 4-1 to conditionally approve Corscale's data center plan on 157 acres off Highland Street, behind WITF. Corscale must meet 17 conditions before the final plan is signed and recorded, and it still needs state permits.

Nov 4, 2026Source

🗺️ Zoning change

Swatara Township's planning commission received a proposed zoning change that could allow another data center campus on three properties along Pennhar Drive and Rupp Hill Road. The commission had not reviewed it yet. Commissioners make the final decision.

Nov 2026Source

🤝 Agreement with the company

Swatara Township commissioners voted 4-1 to approve community benefits agreements with Corscale Data Centers worth about $120.3 million for its two planned data center sites (Highlands West on the old golf course, and Highlands East). The money comes in steps as building goes ahead and would pay for police and fire buildings, roads and other needs. Residents had asked for a delay; that motion failed 4-1.

Oct 7, 2026Source
Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Swatara Township.
  2. Go to township meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Swatara Township. Nothing else.

⚡ Your electric company

PPL Electric Utilities Corp. (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.

🙋 Open tasks here

  • Where will its water and power come from?
  • How much water and how many backup generators would the golf course site use?
  • Corscale has given two totals for both Swatara sites ($10.5 billion in Sept. 2026 and $14.5 billion in Oct. 2026). Which is current?
  • What did the Swatara Township Planning Commission recommend on the golf course data center plan at its Nov. 10, 2026 meeting, and when will commissioners vote?
  • Who is the tenant that will use the data centers?
  • How many megawatts of power will the site use?
  • Did Swatara Township sign an agreement with the developer to keep the plans private (NDA)?
  • Will new power lines be needed to serve the site?
  • Corscale has given two totals for both Swatara sites ($10.5 billion in Sept. 2026 and $14.5 billion in Oct. 2026). Which is current?
  • What are the 17 conditions Swatara Township attached to its Nov. 4, 2026 approval of the Highland Street data center?