Send us a tip
ProposedBig (AI-size): 250 acres

HCI DP Land Acquisition data center (South Hanover Township quarry)

A developer wants to put a data center on a 249.5-acre former quarry in South Hanover Township instead of warehouses. It also filed a legal challenge saying the township's zoning illegally leaves out data centers.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of South Hanover Township.

Where things stand: Proposed Two applications filed June 2026: a special exception for a 249.5-acre quarry site and a challenge to township zoning for a larger area.

❓ 2 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (June 23, 2026): Crowd packed township building after supervisors announced the two applications.

What we know

  • 📍 WhereFormer Pennsy Supply quarry on Wagner Avenue, between Grandview Road and Swatara Creek (Dauphin County parcel 56-016-058, about 252 acres), South Hanover Township, Dauphin County
  • 🏢 CompanyHCI DP Land Acquisition LLC
  • 🌳 Size250 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

    What happened so far

    • June 23, 2026
      Crowd packed township building after supervisors announced the two applications.

    Local votes and rules

    📜 Data center rules

    South Hanover Township voted 5-0 to advertise a data center overlay zone ordinance. It would require special approval, a 400-foot setback from homes, and a 55-foot height limit. A Texas-based developer wants to build two data centers on a former quarry site along Wagner Avenue.

    July 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Developer submits applications for multiple data centers in Dauphin County · CBS 21 (WHP) · June 24, 2026
    2. Data center law proposal draws crowd in Dauphin County, Pa. (from PennLive) · PennLive (via Government Technology) · July 2, 2026
    3. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
    4. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026
    5. Dauphin County parcels (parcel 56-016-058, Pennsy Supply Inc., 252.2 acres, Wagner Ave, South Hanover) · Dauphin County via PASDA · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.