Send us a tip
Approved, not built yetBig (AI-size): 157 acres

Corscale Highlands East data center (Highland Street, Swatara Township)

Also called: Highlands East Data Center, 4951 Highland Street site (behind WITF)

A Texas-based company, Corscale, plans two large one-story data center buildings on 157 acres off Highland Street, behind WITF, in Swatara Township. Township commissioners gave conditional approval on Nov. 4, 2026. The company says the buildings would use about 7,500 gallons of water a day and get power from the grid.

✔ ConfirmedSourceLast checked: Nov 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Swatara Township.

Where things stand: Approved, not built yet Township commissioners voted 4-1 on Nov. 4, 2026 to conditionally approve the land development plan. Corscale must meet 17 conditions before the plan is signed and recorded, and still needs state permits.

  • Nov 9, 2026: Our records now list Corscale Highlands East data center (Highland Street, Swatara Township) as approved Source
  • Nov 4, 2026: Swatara, Dauphin County: project approved Source

❓ 6 open questions about it: see below.

Last checked Nov 9, 2026.

🕒 Latest update (Nov 4, 2026): Swatara Township commissioners voted 4-1 to conditionally approve Corscale's data center plan on the 157-acre field behind WITF. Corscale must meet 17 conditions before the township signs and records the final land development plan. The company still needs state permits. A local paper said topsoil removal could start as soon as December.

What we know

  • 📍 Where4951 Highland Street, behind WITF, next to Route 283 and near Lower Swatara Township, Swatara Township, Dauphin County
  • 🏢 CompanyCorscale Data Centers
  • 👤 Built forunknown (developer says a tenant is in mind, no signed deal)
  • 🌳 Size157 acres
  • 🔌 Where the power comes fromPower from the public grid (PPL). The developer says there would be no power plant on site. It would pay for an on-site substation and switch station.
  • 💧 Water7,500 gallons a day
  • ❄️ Coolingclosed-loop cooling with chillers on the roof
  • 🛢️ Diesel generators12
  • 💵 Cost$10.5 billion
  • 💸 Tax breaksNot a tax break, but Corscale agreed to pay Swatara Township about $120.3 million under community benefits agreements for both of its sites ($36.15 million tied to Highlands East). Payments come in steps as building goes ahead.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Who is the tenant that will use the data centers? 🙋 I'll find out ·
  • How many megawatts of power will the site use? 🙋 I'll find out ·
  • Did Swatara Township sign an agreement with the developer to keep the plans private (NDA)? 🙋 I'll find out ·
  • Will new power lines be needed to serve the site? 🙋 I'll find out ·
  • Corscale has given two totals for both Swatara sites ($10.5 billion in Sept. 2026 and $14.5 billion in Oct. 2026). Which is current? 🙋 I'll find out ·
  • What are the 17 conditions Swatara Township attached to its Nov. 4, 2026 approval of the Highland Street data center? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Sept 2026
      Corscale said it would spend $10.5 billion on its two Swatara Township data center sites (this one and the golf course site).
    • Sept 8, 2026
      Corscale showed its 121-page land development plan for two buildings on Highland Street to the township planning commission. Residents asked about noise, generators, water and who the tenant is.
    • Oct 7, 2026
      Township commissioners voted 4-1 to approve community benefits agreements with Corscale worth about $120.3 million for both sites, $36.15 million of it tied to Highlands East. The agreement is separate from land development approval.
    • Oct 8, 2026
      Corscale held a drop-in information session. It said buildings would sit at least 210 feet from the road behind a 70-foot tree buffer, that PPL confirmed power is available, and that building would start in 2027 and finish in 2029.
    • Nov 4, 2026
      Swatara Township commissioners voted 4-1 to conditionally approve Corscale's data center plan on the 157-acre field behind WITF. Corscale must meet 17 conditions before the township signs and records the final land development plan. The company still needs state permits. A local paper said topsoil removal could start as soon as December.

    Local votes and rules

    ✅ Approved

    Swatara Township commissioners voted 4-1 to conditionally approve Corscale's data center plan on 157 acres off Highland Street, behind WITF. Corscale must meet 17 conditions before the final plan is signed and recorded, and it still needs state permits.

    Nov 4, 2026

    🗺️ Zoning change

    Swatara Township's planning commission received a proposed zoning change that could allow another data center campus on three properties along Pennhar Drive and Rupp Hill Road. The commission had not reviewed it yet. Commissioners make the final decision.

    Nov 2026

    🤝 Agreement with the company

    Swatara Township commissioners voted 4-1 to approve community benefits agreements with Corscale Data Centers worth about $120.3 million for its two planned data center sites (Highlands West on the old golf course, and Highlands East). The money comes in steps as building goes ahead and would pay for police and fire buildings, roads and other needs. Residents had asked for a delay; that motion failed 4-1.

    Oct 7, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something