Microsoft Alviso data center campus (SJC02/SJC03)
San Jose, Santa Clara County
for Microsoft
🕒 June 10, 2026: Microsoft broke ground on the campus.
ProposedSan Jose Data Center 04 (Orchard Parkway)
San Jose, Santa Clara County
22.29 acres
🕒 Feb 9, 2023: The Energy Commission started an environmental report (EIR) on the project.
ProposedPrologis STEM Park at Zanker Road and Highway 237
San Jose, Santa Clara County
159 acres
🕒 Nov 10, 2025: The city announced Prologis as the preferred developer for the site, with a council hear…
Reported in the news, not confirmed yet
ProposedPrologis data center at 5977 Silver Creek Valley Road
San Jose, Santa Clara County
🕒 July 13, 2026: Prologis filed a special use permit (SP26-016) for a three-story, 516,000-square-foot da…
Approved, not built yetBowers data center (2805 Bowers Avenue)
Santa Clara, Santa Clara County
🕒 Feb 9, 2026: A CoreSite company bought 2805 and 2855 Bowers Ave and 2710 Walsh Ave for about $100 mil…
Approved, not built yetPrime data center at 1231 Comstock Street
Santa Clara, Santa Clara County
1.37 acres
🕒 Dec 3, 2024: City Council overturned the Planning Commission's denial and approved the data center.
Built & runningVantage CA3 data center (2590 Walsh Avenue)
Santa Clara, Santa Clara County
🕒 Aug 10, 2022: The California Energy Commission voted to exempt the project's 96 MW of backup generator…
Built & runningCoreSite SV9 data center
Santa Clara, Santa Clara County
🕒 May 23, 2023: CoreSite said SV9 was under construction, with building permits from 2022.
Local votes and rules
⏸️ Pause on new data centers · Gilroy
Council voted unanimously to pause new data centers for 45 days. It can be extended up to two years. The Amazon data center already being built is not affected.
📜 Data center rules · San Jose
A council committee asked staff to add community benefits, like parks and job training, to the data center rules being written. The rules go to council in December 2026.
✅ Approved · San Jose
The city approved Microsoft's Alviso data center campus using an update to its 2022 environmental report.
✅ Approved · Santa Clara
Council overturned the Planning Commission's 'no' vote and approved the Prime data center at 1231 Comstock St.
✅ Approved · Santa Clara
Council approved the 2805 Bowers Ave data center unanimously, even though the Planning Commission did not recommend it.