Amazon data center at 8050 Camino Arroyo, Gilroy
Also called: AWS Gilroy Data Center
Amazon is building two data center buildings (about 438,500 square feet in total) on 56 acres in northeast Gilroy. It would use up to 98 megawatts when finished. The city approved it at staff level in 2023, so there were no public hearings. Amazon has also started early talks about a second site nearby.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Gilroy City.
Where things stand: Being built City staff approved it in July 2023 without a public hearing. Building permits were final in March 2026 and construction is under way.
- Oct 19, 2026: Gilroy, Santa Clara County: moratorium adopted Source
❓ 3 open questions about it: see below.
Last checked Nov 1, 2026.
🕒 Latest update (Oct 19, 2026): City Council extended its data center pause to Sept. 3, 2027. This project is not covered because it was already approved and under construction.
What we know
- 📍 Where8050 Camino Arroyo, near the Leavesley Road exit of Highway 101, northeast Gilroy, Gilroy, Santa Clara County
- 🏢 CompanyAmazon Data Services
- 🏛️ Owned byAmazon
- 👤 Built forAmazon
- 🌳 Size56 acres
- ⚡ Power it needs98 megawatts (about as much as 78,400 homes)
- ❄️ CoolingMostly air cooling; water is used on the hottest days, about 3% of the time (company figures)
- 💵 Cost$2 billion
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many diesel backup generators will the site have? 🙋 I'll find out ·
- When will the first building open? 🙋 I'll find out ·
- Which utility will supply the power, and will new power lines be built? 🙋 I'll find out ·
What happened so far
- 2020Amazon applied to the City of Gilroy for a data center on a 56-acre site.
- July 3, 2023The city's community development director approved the project at staff level. There was no Planning Commission or City Council vote.
- March 2026Building permits were finalized; cranes were on site by April.
- Oct 19, 2026City Council extended its data center pause to Sept. 3, 2027. This project is not covered because it was already approved and under construction.
Local votes and rules
⏸️ Pause on new data centers
Gilroy City Council voted unanimously on Oct. 19, 2026 to extend its pause on new data centers until Sept. 3, 2027, while staff write rules. It can be extended once more for 12 months. The Amazon data center already under construction is not covered; a possible second Amazon site at Highway 152 and Camino Arroyo is.
⏸️ Pause on new data centers
Council voted unanimously to pause new data centers for 45 days. It can be extended up to two years. The Amazon data center already being built is not affected.
Drag the slider to compare the land before and now.
Where this comes from
- $2 billion Amazon data center approved without public meetings or votes · Palo Alto Daily Post · Aug 11, 2026
- Gilroy extends data center moratorium · Local News Matters (Bay City News) · Oct 21, 2026
- Gilroy considers moratorium on new data centers · NBC Bay Area · Sept 14, 2026
- Census geocoder result for 8050 Camino Arroyo, Gilroy · U.S. Census Bureau · Nov 1, 2026