Bowers data center (2805 Bowers Avenue)

Also called: Bowers Data Center, Bowers Backup Generating Facility

GI Partners won approval to tear down an office building and build a four-story, 244,000-square-foot data center with 32 backup generators and its own substation. A CoreSite company bought the land in 2026. It is not clear yet if CoreSite will build the same plan.

โœ” ConfirmedSourceLast checked: Oct 2026

Where things stand: City Council approved it in August 2024; the land was sold to a CoreSite company in early 2026. No building start reported.

๐Ÿ•’ Latest update (Feb 9, 2026): A CoreSite company bought 2805 and 2855 Bowers Ave and 2710 Walsh Ave for about $100 million.

What we know

  • ๐Ÿ“ Where2805 Bowers Avenue, Santa Clara (parcel 216-28-063), Santa Clara, Santa Clara County
  • ๐Ÿข CompanyGI Partners
  • โšก Power it needs72 megawatts (about as much as 57,600 homes)
  • ๐Ÿ”Œ Where the power comes fromSilicon Valley Power, with a new on-site substation paid for by the developer
  • ๐Ÿ—ผ New power linesYes
  • โ„๏ธ Cooling42 air-cooled rooftop chillers
  • ๐Ÿ›ข๏ธ Diesel generators32

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Aug 2024
    Santa Clara City Council approved the data center unanimously, even though the Planning Commission did not recommend it.
  • Feb 9, 2026
    A CoreSite company bought 2805 and 2855 Bowers Ave and 2710 Walsh Ave for about $100 million.

Local votes and rules

โœ… Approved

Council overturned the Planning Commission's 'no' vote and approved the Prime data center at 1231 Comstock St.

Dec 3, 2024

โœ… Approved

Council approved the 2805 Bowers Ave data center unanimously, even though the Planning Commission did not recommend it.

Aug 2024
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Council approves data center in spite of Planning Commission objection ยท Silicon Valley Voice ยท Aug 30, 2024
  2. CoreSite drops $100 million on Santa Clara tech strip ยท Hoodline ยท Feb 9, 2026
  3. Parcel 216-28-063 (2805 Bowers Av, 5.1 acres) ยท Santa Clara County GIS ยท Oct 8, 2026

See something wrong? Tell us and we'll fix it.