Built & running

CoreSite SV9 data center

CoreSite built its ninth Santa Clara data center, SV9, a building of about 230,000 square feet with 34 megawatts of computer power and its own substation. Trackers say it opened in 2025.

โœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Trackers list it as opened in 2025.

๐Ÿ•’ Latest update (May 23, 2023): CoreSite said SV9 was under construction, with building permits from 2022.

What we know

  • ๐Ÿ“ Where2915 Stender Way, Santa Clara, Santa Clara, Santa Clara County
  • ๐Ÿข CompanyCoreSite
  • โšก Power it needs34 megawatts (about as much as 27,200 homes)
  • ๐Ÿ”Œ Where the power comes fromSilicon Valley Power, with a new substation on site
  • ๐Ÿ—ผ New power linesYes

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • May 23, 2023
    CoreSite said SV9 was under construction, with building permits from 2022.

Local votes and rules

โœ… Approved

Council overturned the Planning Commission's 'no' vote and approved the Prime data center at 1231 Comstock St.

Dec 3, 2024

โœ… Approved

Council approved the 2805 Bowers Ave data center unanimously, even though the Planning Commission did not recommend it.

Aug 2024
๐Ÿ›ฐ๏ธ See it from above

Drag the slider to compare the land before and now.

20182025
Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. CoreSite expands data center footprint in Silicon Valley and Denver campuses ยท CoreSite ยท May 23, 2023
  2. Data centers in California ยท Cleanview ยท 2026

See something wrong? Tell us and we'll fix it.