No project in Haymarket Town, but 18 nearby

Who decides here: the Town Council of Haymarket Town votes on zoning. The Prince William County may review big projects too.

Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.

Nearby (within 15 miles)

Proposedabout 1 miles away

Gardner Property data centers (former Hillwood campground, Gainesville)

Prince William County, Prince William County

82 acres

🕒 Aug 13, 2026: Developer held a community meeting.

Being builtabout 2 miles away

NTT Grove at Gainesville campus (I-66 and U.S. 29)

Prince William County, Prince William County

102 acres

🕒 July 2024: First building was rising along I-66.

Reported in the news, not confirmed yet

Proposedabout 3 miles away

Microsoft data center near Gainesville (University Boulevard south of I-66)

Prince William County, Prince William County

123 acres · for Microsoft

🕒 July 2026: State regulators opened public comment (until August 7) on Microsoft's request to fill 9…

Reported in the news, not confirmed yet

Being builtabout 6 miles away

Microsoft data center on Jacksonville Avenue

Prince William County, Prince William County

46 acres · for Microsoft

🕒 Jan 2024: Site preparation began.

Reported in the news, not confirmed yet

Status unclearabout 10 miles away

Amazon data center on Blackwell Road (Warrenton)

Warrenton, Fauquier County

42 acres · for Amazon Web Services

🕒 July 30, 2026: Judge denied a residents' group's request to join Amazon's appeal.

Stopped or cancelledabout 11 miles away

Gigaland data center (Remington)

Fauquier County, Fauquier County

200 acres

🕒 Aug 17, 2026: Developer withdrew again before the September hearing.

Reported in the news, not confirmed yet

Approved, not built yetabout 11 miles away

Devlin Technology Park (Bristow)

Prince William County, Prince William County

270 acres · for Amazon Web Services

🕒 Nov 2025: Amazon Data Services bought most of the site for about $700 million.

Approved, not built yetabout 11 miles away

LHR Gainesville data center campus (Linton Hall Road, Bristow)

Prince William County, Prince William County

196 acres

🕒 Oct 2025: Army Corps of Engineers took public comments on a wetlands permit.

Reported in the news, not confirmed yet

Stopped or cancelledabout 11 miles away

Convergent Technology Park (south of Remington)

Fauquier County, Fauquier County

100 acres

🕒 Aug 27, 2026: Developer withdrew the rezoning.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelledHollow dot (when zoomed in): exact site not known yet, pin shows the town

What you can do

  1. Get told first.
    We'll email you if anything changes in Haymarket Town.
  2. Go to council meetings.
    Anyone can speak. Big projects usually need a public hearing.
  3. Ask questions in writing.
    Use our checklist.
📣 Report something here

🔔 Get told first

We'll email you when something changes in Haymarket Town. Nothing else.

⚡ Your electric company

Virginia Electric & Power Co. (company).

Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.