Devlin Technology Park (Bristow)

Supervisors rezoned the Devlin Road site in Bristow from homes to data centers in November 2023. Neighbors sued, but the circuit court and the Court of Appeals upheld the rezoning. In 2025 Amazon Data Services bought about 70% of the 270-acre site for about $700 million.

βœ” ConfirmedSourceLast checked: Oct 7, 2026

Where things stand: Rezoned in November 2023; courts upheld it. Amazon bought most of the land in 2025.

πŸ•’ Latest update (Nov 2025): Amazon Data Services bought most of the site for about $700 million.

What we know

  • πŸ“ WhereNear Devlin Road south of I-66, Bristow, Prince William County, Prince William County
  • 🏒 CompanyStanley Martin Homes (rezoning applicant)
  • πŸ‘€ Built forAmazon Web Services
  • 🌳 Size270 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Nov 2023
    Board of County Supervisors rezoned the site for data centers.
  • Sept 2025
    Virginia Court of Appeals upheld the rezoning.
  • Nov 2025
    Amazon Data Services bought most of the site for about $700 million.

Local votes and rules

πŸ—ΊοΈ Zoning change

Supervisors unanimously shrank the Data Center Opportunity Zone Overlay District from about 9,700 to 3,500 acres. Most new data centers will now need a special use permit with a public hearing. Projects already filed get a 90-day grace period.

Sept 22, 2026

βœ‹ Turned down

Supervisors voted 8-0 to reject a land-use plan change for the Dulles South Innovation Center, a proposed campus of about 43 million square feet of data centers on 1,940 acres of homes and farms near Sanders Lane (Gainesville District).

July 7, 2026

βš–οΈ Court case

Neighbors sued over the county's December 2023 rezoning for the 2,100-acre Prince William Digital Gateway. A judge voided it because the newspaper notices were not spaced far enough apart, and the Court of Appeals agreed on March 31, 2026. The county stopped defending it in April, and QTS dropped its last appeal on July 2, 2026, ending the project.

March 31, 2026

πŸ“œ Data center rules

Supervisors voted 5-2 to update the noise law so data center cooling systems must meet noise limits around the clock: 73 decibels by day and 68 at night, measured on the 'C' scale that captures low hum. Residents and the county's advisory group had asked for a stricter method.

Oct 2025
πŸ›°οΈ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something

Where this comes from

  1. Amazon Buys Bristow Data Center Site for Record $700 Million Β· Northern Virginia Magazine Β· Nov 4, 2025