Gardner Property data centers (former Hillwood campground, Gainesville)

JK Land Holdings wants to rezone the former Hillwood Camping Park in Gainesville for up to five data centers (up to 2 million square feet, up to 81 feet tall) and a substation. The campground, where people lived long-term in trailers, closed. The site is outside the county's data center zone.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Prince William County Board of Supervisors (for land outside city and town limits).

Where things stand: Proposed Refiled in 2026; community meeting August 13, 2026; expected before supervisors in fall 2026.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Aug 13, 2026): Developer held a community meeting.

What we know

  • 📍 WhereFormer Hillwood Camping Park, 14280 Gardner Manor Place, Gainesville, Prince William County, Prince William County
  • 🏢 CompanyJK Land Holdings
  • 🌳 Size82 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • When will the Planning Commission and supervisors vote? 🙋 I'll find out ·
  • Who will use the data centers? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 27, 2022
      Developer first submitted the plan to the county.
    • Aug 13, 2026
      Developer held a community meeting.

    Local votes and rules

    🗺️ Zoning change

    Supervisors unanimously shrank the Data Center Opportunity Zone Overlay District from about 9,700 to 3,500 acres. Most new data centers will now need a special use permit with a public hearing. Projects already filed get a 90-day grace period.

    Sept 22, 2026

    ✋ Turned down

    Supervisors voted 8-0 to reject a land-use plan change for the Dulles South Innovation Center, a proposed campus of about 43 million square feet of data centers on 1,940 acres of homes and farms near Sanders Lane (Gainesville District).

    July 7, 2026

    ⚖️ Court case

    Neighbors sued over the county's December 2023 rezoning for the 2,100-acre Prince William Digital Gateway. A judge voided it because the newspaper notices were not spaced far enough apart, and the Court of Appeals agreed on March 31, 2026. The county stopped defending it in April, and QTS dropped its last appeal on July 2, 2026, ending the project.

    March 31, 2026

    📜 Data center rules

    Supervisors voted 5-2 to update the noise law so data center cooling systems must meet noise limits around the clock: 73 decibels by day and 68 at night, measured on the 'C' scale that captures low hum. Residents and the county's advisory group had asked for a stricter method.

    Oct 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Plan for data centers at Hillwood campground is back · Prince William Times · Aug 17, 2026
    2. 5 data centers pitched for Gardner Property in Gainesville · InsideNoVa · Aug 18, 2026
    3. Gardner Property campus, 14280 Gardner Manor Pl, Gainesville · Datacentermap · Oct 8, 2026
    4. Nominatim geocode: 14280 Gardner Manor Pl · OpenStreetMap Nominatim · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.