No project in Herndon Town, but 9 nearby
Who decides here: the Town Council of Herndon Town votes on zoning. The Fairfax County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Prologis Concorde Industrial Park data center conversion (Sterling)
Loudoun County, Loudoun County
17 acres
🕒 Feb 11, 2026: Board of Supervisors held its review of the rezoning.
Being builtabout 4 miles awayEdgeCore AS01 and AS02 data centers (Sterling)
Loudoun County, Loudoun County
🕒 April 2026: EdgeCore secured $1.5 billion in loans to build AS01 and AS02.
Reported in the news, not confirmed yet
Proposedabout 5 miles awayStarwood data center on county police training land (3721 Stonecroft Blvd, Chantilly)
Fairfax County, Fairfax County
41.7 acres
🕒 March 17, 2026: Board of Supervisors voted 9-0 to approve the land sale.
Proposedabout 7 miles awayAmazon Bridgefield Tech Center (former GW Virginia campus, Ashburn)
Loudoun County, Loudoun County
122 acres · for Amazon Web Services
🕒 July 28, 2026: Amazon filed a first plan for four data center buildings (805,092 square feet).
Proposedabout 10 miles awayServerfarm data center at 7980-7990 Quantum Drive (Tysons)
Fairfax County, Fairfax County
14.4 acres
🕒 March 11, 2026: Serverfarm's attorney filed a statement supporting its special exception request.
Reported in the news, not confirmed yet
Proposedabout 12 miles awayStarwood Word of Grace data center (Renaissance Tech Park, Herndon area)
Fairfax County, Fairfax County
8 acres
🕒 Dec 2025: Starwood filed site plans and an initial air permit.
Reported in the news, not confirmed yet
Proposedabout 13 miles awayLeesburg Gateway data center plan (Peterson Companies)
Leesburg, Loudoun County
107 acres
🕒 Jan 26, 2026: Town Council cancelled its public hearing at the developer's request.
What you can do
- Get told first.
We'll email you if anything changes in Herndon Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Virginia Electric & Power Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Virginia.