Send us a tip
Proposed

Starwood Word of Grace data center (Renaissance Tech Park, Herndon area)

A Starwood company filed plans for two data center buildings on the former Word of Grace Christian Church site, an 8-acre lot inside its 60-acre Renaissance Tech Park. The first building would be about 406,000 square feet using 60 MW; the second 32 MW.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Fairfax County Board of Supervisors (for land outside city and town limits).

Where things stand: Proposed Site plans and a first air permit filed in late 2025.

❓ 2 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Dec 2025): Starwood filed site plans and an initial air permit.

What we know

  • 📍 WhereFairfax County, Fairfax County
  • 🏢 CompanyStarwood Capital Group
  • 🌳 Size8 acres
  • ⚡ Power it needs92 megawatts (about as much as 73,600 homes)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the site inside the Town of Herndon or unincorporated Fairfax County? 🙋 I'll find out ·
  • Is the Word of Grace data center site 8 acres or about 30 acres? Reports differ. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 2025
      Starwood filed site plans and an initial air permit.

    Local votes and rules

    📜 Data center rules

    Supervisors adopted new zoning rules for data centers: at least 200 feet from homes, at least 1 mile from Metro stations, noise studies required, and outdoor equipment such as generators and cooling units set back 500 feet.

    Sept 10, 2024
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Starwood Files Plans for Two-Building "Word of Grace" Data Center · BLDUP · Dec 2, 2025
    2. Herndon site near future Western High School deemed suitable for data center · FFXnow · Dec 16, 2025
    3. Starwood to Convert Former NFL Facility Into More Data Centers · Commercial Observer · Dec 2025

    See something wrong? Tell us and we'll fix it.