Starwood Word of Grace data center (Renaissance Tech Park, Herndon area)

A Starwood company filed plans for two data center buildings on the former Word of Grace Christian Church site, an 8-acre lot inside its 60-acre Renaissance Tech Park. The first building would be about 406,000 square feet using 60 MW; the second 32 MW.

๐Ÿ‘ฅ Reported, not confirmed yetSourceLast checked: Oct 7, 2026

Where things stand: Site plans and a first air permit filed in late 2025.

๐Ÿ•’ Latest update (Dec 2025): Starwood filed site plans and an initial air permit.

What we know

  • ๐Ÿ“ WhereFairfax County, Fairfax County
  • ๐Ÿข CompanyStarwood Capital Group
  • ๐ŸŒณ Size8 acres
  • โšก Power it needs92 megawatts (about as much as 73,600 homes)

โ“ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • Dec 2025
    Starwood filed site plans and an initial air permit.

Local votes and rules

๐Ÿ“œ Data center rules

Supervisors adopted new zoning rules for data centers: at least 200 feet from homes, at least 1 mile from Metro stations, noise studies required, and outdoor equipment such as generators and cooling units set back 500 feet.

Sept 10, 2024
๐Ÿ›ฐ๏ธ See it from above

An aerial photo of the area.

We only know the town, so this shows the town center, not the exact site. Photos: USGS The National Map.

Live near here?

Tell us what you see, hear, or what your bill looks like.

๐Ÿ“ฃ Report something

Where this comes from

  1. Starwood Files Plans for Two-Building "Word of Grace" Data Center ยท BLDUP ยท Dec 2, 2025

See something wrong? Tell us and we'll fix it.