No project in Granger City, but 9 nearby
Who decides here: the City Council of Granger City votes on zoning. The Williamson County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Iron Mountain 'Taylor Meadows' data center campus (FM 3349, near Hutto and Taylor)
Unincorporated Williamson County, Williamson County
500 acres
🕒 March 2026: Iron Mountain presented the Taylor Meadows project to Hutto City Council with a sewer se…
Reported in the news, not confirmed yet
Approved, not built yetabout 11 miles awayBlueprint data center campus (MLK Jr. Drive, Taylor)
Taylor, Williamson County
🕒 Oct 2025: A state district judge dismissed a lawsuit against Blueprint.
Approved, not built yetabout 11 miles away'Project Mustang' data center campus (east of Taylor)
Unincorporated Williamson County, Williamson County
665 acres
🕒 Oct 8, 2026: Taylor City Council voted 5-0 to approve an agreement with Big Watt Digital and PowerHou…
Approved, not built yetabout 12 miles awayKDC 'Project Comal' data center campus (Taylor)
Taylor, Williamson County
220 acres
🕒 March 26, 2026: Taylor City Council voted unanimously to annex and zone the land for the data center.
Reported in the news, not confirmed yet
Being builtabout 13 miles awaySkybox PowerCampus Austin (Hutto)
Hutto, Williamson County
220 acres
🕒 Nov 2023: State filing for the first Hutto building; construction set for Jan. to Nov. 2024.
Reported in the news, not confirmed yet
Approved, not built yetabout 14 miles awayMesone data center (County Road 305, Jarrell)
Jarrell, Williamson County
150 acres
🕒 Oct 14, 2025: City Council annexed the land and changed its land use and zoning to allow the data cent…
Reported in the news, not confirmed yet
Approved, not built yetabout 14 miles awaySkybox 'Project Sequel' data center campus (Hutto Megasite)
Hutto, Williamson County
140 acres
🕒 Oct 2026: Hutto City Council voted 6-0 to rezone the 140-acre Megasite tract as a planned developm…
Reported in the news, not confirmed yet
What you can do
- Get told first.
We'll email you if anything changes in Granger City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Granger City: Oncor Electric Delivery Company LLC (company) or City of Bartlett (not available) or Pedernales Electric Co-op, Inc. (co-op (owned by its members)) or Bluebonnet Electric Co-op, Inc. (co-op (owned by its members)) or Bartlett Electric Co-op, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.