Blueprint data center campus (MLK Jr. Drive, Taylor)

Also called: Blueprint Projects Taylor, Blueprint Data Centers

Blueprint plans a data center campus at 1601 Martin Luther King Jr. Drive in Taylor, built in three phases to 135,000 square feet. It expects to invest up to $1 billion over ten years. The land had been planned for a future park, which sparked a resident petition and a lawsuit that a judge dismissed.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Taylor City.

Where things stand: Approved, not built yet Taylor City Council approved it July 24, 2025; a resident lawsuit was later dismissed.

❓ 3 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Oct 2025): A state district judge dismissed a lawsuit against Blueprint.

What we know

  • 📍 Where1601 Martin Luther King Jr. Drive, Taylor, Williamson County
  • 🏢 CompanyBlueprint Data Centers
  • ⚡ Power it needs60 megawatts (about as much as 48,000 homes)
  • 🔌 Where the power comes fromOncor power agreement for 30 MW, hoping for 60 MW
  • 💵 Cost$1 billion
  • 💸 Tax breaksThe company secured tax breaks in 2024 (terms not reported here).
  • 👷 Jobs promised30

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Is the site 52 acres or 87 acres? Reports differ. 🙋 I'll find out ·
  • What tax break did Taylor give, and on what terms? 🙋 I'll find out ·
  • How much water will it use? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • July 24, 2025
      Taylor City Council unanimously approved the data center.
    • Oct 2025
      A state district judge dismissed a lawsuit against Blueprint.

    Local votes and rules

    🤝 Agreement with the company

    Taylor City Council voted 5-0 to approve a 20-year agreement to annex the 664-acre Taylor Technology Campus ('Project Mustang') planned by Big Watt Digital and PowerHouse Data Centers. The city says this lets it enforce rules on noise, water and air. The developers promised about $28.2 million for schools, city projects and community programs. Many residents asked for a delay.

    Oct 8, 2026

    🗳️ Public vote

    Residents turned in a petition with more than 1,400 signatures for a citizen ordinance that would pause data centers in Taylor until the city creates a special zoning district for them. City Council did not adopt it or put it on the ballot, saying Texas law does not let cities change zoning by popular vote. Council members said they will handle data centers through the city plan and development code instead.

    July 9, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Blueprint Projects gets greenlight for data center in Taylor, Texas · DatacenterDynamics · July 28, 2025
    2. Taylor data center developer drops annexation request, moves project outside city · Austin American-Statesman · Sept 6, 2026
    3. Texas data centers map and list · Cleanview (tracker) · Oct 2026