2 data center projects in Abilene City
Who decides here: the City Council of Abilene City votes on zoning. The Taylor County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Abilene City
Stargate AI data center campus (Lancium Clean Campus, Abilene)
Abilene, Taylor County
800 acres · for Oracle for OpenAI
🕒 Oct 22, 2026: By Oct. 22, the state had suspended at least 17 data center permits issued after the pau…
Being builtCrusoe 900 MW AI campus for Microsoft (Abilene)
Abilene, Taylor County
for Microsoft
🕒 March 27, 2026: Crusoe announced a 900-megawatt expansion in Abilene for Microsoft, with its own on-site…
Nearby (within 15 miles)
Vantage 'Frontier' AI data center campus (Shackelford County)
Unincorporated Shackelford County, Shackelford County
1,200 acres · for Oracle / OpenAI (reported)
🕒 Sept 22, 2026: TCEQ mailed its notice of the application and preliminary decision on a major air permit…
Proposedabout 14 miles awayPowerPlay AI and Sharon AI gas-powered data center (near Abilene)
Unincorporated Taylor County, Taylor County
🕒 July 2026: PowerPlay AI and Sharon AI announced the 400 MW joint venture.
Reported in the news, not confirmed yet
Local votes and rules
🤝 Agreement with the company
Abilene City Council approved an 85% property tax break for the Stargate data center campus built by Crusoe on land owned by Lancium, with Oracle as the main tenant. To qualify, Crusoe must spend at least $2.4 billion of a planned $3.5 billion and create 357 full-time jobs paying at least $57,600.
What you can do
- Get told first.
We'll email you if anything changes in Abilene City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Abilene City: Coleman County Electric Co-op, Inc. (not available) or AEP Texas North Company (company) or Taylor Electric Co-op Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.
🙋 Open tasks here
- How much water does the campus use each day, and from which supplier?
- How many gas turbines and diesel generators run on site, and how much do they emit?
- Did any city official sign an agreement to keep the plans private (NDA)?
- Are the new Buildings 9 and 10 at 5502 Spinks Road part of Crusoe's Microsoft expansion or more buildings for the first campus?
- Was this site's state stormwater permit one of the at least 17 data center permits the state (TCEQ) suspended in October 2026?
- What fuel will the 900-megawatt on-site power plant burn, and what air permit does it need?
- How much water will it use?
- Will the city give this expansion a tax break too?