Being builtBig (AI-size): 1,400 megawatts

Vantage 'Frontier' AI data center campus (Shackelford County)

Also called: Frontier, Stargate Frontier

Vantage Data Centers is building a $25 billion campus called Frontier on about 1,200 acres in rural Shackelford County, southwest of Albany. It is planned to have 10 buildings and use about 1.4 gigawatts of power. News reports tie it to the Oracle and OpenAI 'Stargate' project.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Shackelford County Commissioners Court (for land outside city and town limits).

Where things stand: Being built Under construction; first building expected in the second half of 2026, full campus by 2028.

❓ 5 open questions about it: see below.

Last checked Oct 26, 2026.

🕒 Latest update (Sept 22, 2026): TCEQ mailed its notice of the application and preliminary decision on a major air permit for VoltaGrid's power plant for the Vantage Frontier campus. TCEQ had not set a comment deadline as of Oct. 19.

What we know

  • 📍 WherePrivate Road 1604 (175-246 PR 1604), Shackelford County, Unincorporated Shackelford County, Shackelford County
  • 🏢 CompanyVantage Data Centers
  • 🏛️ Owned byDigitalBridge-backed Vantage Data Centers
  • 👤 Built forOracle / OpenAI (reported)
  • 🌳 Size1,200 acres
  • ⚡ Power it needs1,400 megawatts (about as much as 1,120,000 homes)
  • ❄️ CoolingClosed-loop chiller system with air and liquid cooling
  • 💵 Cost$25 billion

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Where will the power come from, and will new power lines or a gas plant be built? 🙋 I'll find out ·
  • How much water will it use, and from where? 🙋 I'll find out ·
  • Did Shackelford County give a tax break? 🙋 I'll find out ·
  • How many diesel backup generators will there be? 🙋 I'll find out ·
  • When will TCEQ set the public comment deadline for the VoltaGrid power plant air permit? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 8, 2026: We checked the site location: exact site found in state records or maps.

    What happened so far

    • Aug 2025
      Vantage announced the $25 billion Frontier campus; construction had already begun.
    • Sept 22, 2026
      TCEQ mailed its notice of the application and preliminary decision on a major air permit for VoltaGrid's power plant for the Vantage Frontier campus. TCEQ had not set a comment deadline as of Oct. 19.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Vantage Data Centers to Build $25 Billion AI Campus in Texas · Pipeline & Gas Journal · Aug 2025
    2. Vantage Data Centers breaks ground on data center campus in Texas · W.Media · 2025
    3. Texas data centers map and list · Cleanview (tracker) · Oct 2026
    4. Epoch AI Frontier Data Centers dataset (CC BY 4.0) · Epoch AI · Oct 8, 2026
    5. TDLR TABS2026024068: Vantage DC Abilene - TX3 - Project Frontier, 246 PR 1604 Bldg 1 · Texas Department of Licensing and Regulation · Oct 8, 2026
    6. StratMap address point 175 PRIVATE ROAD 1604 · Texas Geographic Information Office (StratMap address points) · Oct 8, 2026
    7. Summary: Data Center Permits Issued by TCEQ After 9/21/2026 · Public Citizen (summary of TCEQ records) · Oct 19, 2026
    8. Texas continued permitting data centers after Abbott's pause, report finds · Inside Climate News via KUT · Oct 20, 2026

    See something wrong? Tell us and we'll fix it.