Crusoe 900 MW AI campus for Microsoft (Abilene)
Also called: Abilene Building 9, Abilene DC9
Crusoe is building a second AI campus next to the Stargate site in Abilene, this time for Microsoft. It will have two very large buildings and its own 900-megawatt power plant on site. Crusoe says this brings the whole Abilene site to about 2.1 gigawatts.
Where things stand: Site clearing started in 2026; first building expected online around mid-2027.
๐ Latest update (March 27, 2026): Crusoe announced a 900-megawatt expansion in Abilene for Microsoft, with its own on-site power plant.
What we know
- ๐ WhereSouth side of the existing Lancium/Stargate site, north Abilene, Abilene, Taylor County
- ๐ข CompanyCrusoe
- ๐ค Built forMicrosoft
- โก Power it needs900 megawatts (about as much as 720,000 homes)
- ๐ Where the power comes fromA new 900-megawatt power plant built on site (fuel not stated by the company; news reports guess natural gas).
โ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- What fuel will the 900-megawatt on-site power plant burn, and what air permit does it need? ๐ I'll find out
- How much water will it use? ๐ I'll find out
- Will the city give this expansion a tax break too? ๐ I'll find out
What happened so far
- March 27, 2026Crusoe announced a 900-megawatt expansion in Abilene for Microsoft, with its own on-site power plant.
Local votes and rules
๐ค Agreement with the company
Abilene City Council approved an 85% property tax break for the Stargate data center campus built by Crusoe on land owned by Lancium, with Oracle as the main tenant. To qualify, Crusoe must spend at least $2.4 billion of a planned $3.5 billion and create 357 full-time jobs paying at least $57,600.
Drag the slider to compare the land before and now.
Where this comes from
- Crusoe Announces New 900 MW AI Factory Campus in Abilene, Texas to Support Microsoft AI Infrastructure ยท Crusoe (company) ยท March 27, 2026
- Microsoft takes up residence next to OpenAI, Oracle at Crusoe's 900 MW Texas datacenter expansion ยท The Register ยท March 27, 2026
- Texas data centers map and list ยท Cleanview (tracker) ยท Oct 2026
See something wrong? Tell us and we'll fix it.