2 data center projects in Dallas City
Who decides here: the City Council of Dallas City votes on zoning. The Dallas County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Dallas City
DA12 / DA13 data center buildings (West Mockingbird Lane, Dallas)
Dallas, Dallas County
🕒 Nov 2026: DA12 LLC registered state building plans for DA13-1: a second four-story, 372,443-square…
ProposedCrow Holdings / CleanArc data center campus (Stemmons Corridor, Dallas)
Dallas, Dallas County
40 acres
🕒 Jan 20, 2026: Crow Holdings announced a 245 MW campus; first 70 MW building due late 2027.
Reported in the news, not confirmed yet
Nearby (within 15 miles)
KDC data center on University of Dallas land (Irving)
Irving, Dallas County
67.3 acres
🕒 July 2024: Irving City Council approved rezoning for the data center.
Reported in the news, not confirmed yet
Being builtabout 12 miles awayPowerHouse Irving data center campus (111 Customer Way)
Irving, Dallas County
50 acres
Reported in the news, not confirmed yet
Approved, not built yetabout 12 miles awayMicrosoft data centers (four buildings, Irving)
Irving, Dallas County
for Microsoft
🕒 Dec 12, 2024: Irving City Council approved tax breaks for four Microsoft data centers.
Being builtabout 13 miles awayPrime Data Centers Garland campus (4221 N. Garland Ave.)
Garland, Dallas County
Reported in the news, not confirmed yet
Approved, not built yetabout 13 miles awayQTS Irving campus expansion (three buildings)
Irving, Dallas County
🕒 Dec 12, 2024: Irving City Council approved tax breaks for three QTS data centers.
Being builtabout 14 miles awaySTACK Infrastructure DFW02 campus (Lancaster)
Lancaster, Dallas County
102 acres
Reported in the news, not confirmed yet
Proposedabout 14 miles awayYondr data center campus (Lancaster)
Lancaster, Dallas County
163 acres
Reported in the news, not confirmed yet
Local votes and rules
📌 Other
Five Dallas City Council members asked the city to start changing its development code for data centers. Today data centers count as 'communications exchange facilities' and are allowed without a public hearing in many non-residential and mixed-use areas. The change could create a separate 'data center' land use with its own rules. A council committee discussed it in early September 2026.
What you can do
- Get told first.
We'll email you if anything changes in Dallas City. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Dallas City: Oncor Electric Delivery Company LLC (company) or Texas-new Mexico Power Co. (company) or Trinity Valley Electric Co-op Inc. (co-op (owned by its members)) or Farmers Electric Co-op, Inc. (co-op (owned by its members)) or Hilco Electric Cooperative, Inc. (co-op (owned by its members)).
In much of Texas you can pick who sells you power, but this company owns the power lines.
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Texas.
🙋 Open tasks here
- How much water will it use?
- Who will use it?
- Will the Crow Holdings data center be built on vacant land or on the Dallas Market Center site? A later trade report says new zoning papers point to the market hall site.
- Is Equinix the owner, as data center listings say? The state filings name only DA12 LLC.
- How many megawatts will the two buildings use?
- Has construction started on the first building (DA12)?
- What kind of fuel will the 38 backup generators use, and do they need a state air permit?