Irving approved a 50% tax break for 10 years for four new Microsoft data centers. Microsoft must sign long leases and add at least $200 million in value.

✔ ConfirmedSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Irving City.

Where things stand: Approved, not built yet City Council approved a 10-year, 50% tax break on Dec. 12, 2024.

❓ 2 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Dec 12, 2024): Irving City Council approved tax breaks for four Microsoft data centers.

What we know

  • 📍 WhereIrving, Dallas County
  • 🏢 CompanyMicrosoft
  • 👤 Built forMicrosoft
  • 💸 Tax breaks10-year, 50% city property tax break if Microsoft signs 15-year leases and adds at least $200 million in taxable value by 2027.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Dec 12, 2024
      Irving City Council approved tax breaks for four Microsoft data centers.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Microsoft And QTS Building Over 1M Sq Ft Of Data Center Space · Dallas Express · Dec 18, 2024
    2. Microsoft, QTS To Bring More Than 1M SF Of Data Centers To Irving · Bisnow · Dec 2024

    See something wrong? Tell us and we'll fix it.