ProposedBig (AI-size): 245 megawatts

Crow Holdings / CleanArc data center campus (Stemmons Corridor, Dallas)

Crow Holdings plans a 245-megawatt data center campus on about 40 vacant acres along the Stemmons Freeway in Dallas. The first building is due in late 2027.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Dallas City.

Where things stand: Proposed Announced Jan. 2026; first 70 MW building expected late 2027.

❓ 3 open questions about it: see below.

Last checked Oct 10, 2026.

🕒 Latest update (Jan 20, 2026): Crow Holdings announced a 245 MW campus; first 70 MW building due late 2027.

What we know

  • 📍 WhereAbout 40 acres along the Stemmons Corridor near the Infomart, Dallas, Dallas County
  • 🏢 CompanyCrow Holdings with CleanArc Data Centers
  • 🌳 Size40 acres
  • ⚡ Power it needs245 megawatts (about as much as 196,000 homes)
  • 🔌 Where the power comes fromOwn on-site substation.

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How much water will it use? 🙋 I'll find out ·
  • Who will use it? 🙋 I'll find out ·
  • Will the Crow Holdings data center be built on vacant land or on the Dallas Market Center site? A later trade report says new zoning papers point to the market hall site. 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Jan 20, 2026
      Crow Holdings announced a 245 MW campus; first 70 MW building due late 2027.

    Local votes and rules

    📌 Other

    Five Dallas City Council members asked the city to start changing its development code for data centers. Today data centers count as 'communications exchange facilities' and are allowed without a public hearing in many non-residential and mixed-use areas. The change could create a separate 'data center' land use with its own rules. A council committee discussed it in early September 2026.

    Aug 11, 2026
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    We only know the town, so this shows the town center, not the exact site. Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Crow Holdings announces 245MW flagship data center campus in central Dallas · Crow Holdings (press release) · Jan 20, 2026
    2. Crow Holdings plans 245 MW data center campus in Texas · W.Media · Jan 2026

    See something wrong? Tell us and we'll fix it.