1 data center project in Sugarloaf Township
Who decides here: the Township Supervisors (in some larger townships, the Board of Commissioners) of Sugarloaf Township votes on zoning. The Luzerne County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Project Hazelnut (NorthPoint, Hazle Township)
Hazle Township, Luzerne County
1,280 acres · for Amazon Web Services (reported)
🕒 Nov 9, 2026: Residents packed a township meeting at Hazleton Area High School on the revised data cen…
Stopped or cancelledabout 5 miles awayWest Hazleton data center site (behind Valmont Shopping Plaza)
West Hazleton, Luzerne County
🕒 Dec 2025: Reported as withdrawn.
Reported in the news, not confirmed yet
Proposedabout 5 miles awayHollenback Township landowner rezoning for data centers
Hollenback Township, Luzerne County
460 acres
🕒 Sept 18, 2026: The Times-Tribune listed the Hollenback request (11 data centers on 460 acres) with the …
Reported in the news, not confirmed yet
Proposedabout 5 miles awayNescopeck / Valley View Wood data center (Nescopeck Township)
Nescopeck Township, Luzerne County
Reported in the news, not confirmed yet
Approved, not built yetabout 6 miles awayQTS data center campus (Salem 2), Salem Township
Salem Township, Luzerne County
1,700 acres
🕒 Aug 22, 2026: Developers said construction is planned to begin in late 2026.
Built & runningabout 7 miles awayNautilus Cryptomine (bitcoin mining at Susquehanna nuclear plant)
Salem Township, Luzerne County
for Bitcoin mining
🕒 Oct 2024: TeraWulf sold its 25% share of the Nautilus mine to a Talen Energy company for about $92…
Local votes and rules
🗺️ Zoning change · Luzerne County
Luzerne County is writing data center rules for the 19 towns that use county zoning. Every data center would need a special exception from the county zoning hearing board. The planning commission recommended it in May 2026 and meets Oct. 8 to review new changes from the county law office. County Council must still vote.
🗺️ Zoning change · Luzerne County
The Luzerne County Planning Commission sent the county's data center zoning rules to County Council and recommended adoption. Every data center would need a special exception from the county zoning hearing board. County Council has not set a vote date.
What you can do
- Get told first.
We'll email you if anything changes in Sugarloaf Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- Will the judge let the land buyer continue the appeal?
- Who would build a data center there now?