Proposed

Project Hazelnut (NorthPoint, Hazle Township)

Also called: Project Hazlenut, NP Hazleton Logistics

NorthPoint wanted a 15-building data center campus on about 1,280 acres in Hazle Township. The township said no, and a judge upheld that. The township is now writing data center rules during a 180-day pause.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Township denied it in Nov. 2025 and a county judge agreed, but NorthPoint has appealed to Commonwealth Court, so it is not over. State permits are still under DEP review.

πŸ•’ Latest update (Sept 2026): NorthPoint sent letters to about 4,500 households about the $10,000 offer. Many residents said no. The Commonwealth Court appeal was still pending.

What we know

  • πŸ“ WhereAbout 1,280 acres near the north zone of Humboldt Industrial Park and a planned PPL substation, Hazle Township, Luzerne County
  • 🏒 CompanyNP Hazleton Logistics LLC
  • πŸ›οΈ Owned byNorthPoint Development
  • πŸ‘€ Built forAmazon Web Services (reported)
  • 🌳 Size1,280 acres
  • πŸ”Œ Where the power comes fromPlanned next to a new PPL substation (Tomhicken) and power line
  • πŸ—Ό New power linesYes
  • πŸ’§ WaterTreated wastewater from the Greater Hazleton Joint Sewer Authority for cooling; drinking-type water from CAN DO's industrial park supplier (developer's statement)
  • ❄️ CoolingWater cooling with treated wastewater in warm months, air cooling October to April (developer's statement)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

What happened so far

  • 2025
    NP Hazleton Holdings 1 LLC applied to the Susquehanna River Basin Commission (SRBC) for approval of water use by the data center (Pending No. 2025-149). As of October 2026 it is still listed as pending.
  • Nov 2025
    Supervisors denied land development approval.
  • Feb 18, 2026
    At a state DEP hearing, the developer said cooling water would be treated wastewater from the Greater Hazleton Joint Sewer Authority, up to 2.8 million gallons for all 15 buildings, and that it would pay for the pipeline and plant upgrades. Residents asked how much would evaporate.
  • June 2026
    Luzerne County judge denied the developer's appeal; township declared its zoning invalid on data centers and started a 180-day pause to write rules.
  • June 2026
    NorthPoint offered a $165 million community benefits package, including $10,000 for each eligible township household, if the project is approved. NorthPoint had appealed to Commonwealth Court.
  • Sept 2026
    NorthPoint sent letters to about 4,500 households about the $10,000 offer. Many residents said no. The Commonwealth Court appeal was still pending.

Local votes and rules

⏸️ Pause on new data centers

Hazle Township supervisors unanimously declared parts of the township's zoning invalid because it does not cover data centers. This starts a pause of about 180 days on new data center applications while the planning commission writes new rules.

June 2026

βš–οΈ Court case

A Luzerne County judge denied the Project Hazelnut developer's appeal of the township's rejection. The judge said the project should first go to the township zoning board for a special exception. The developer is now asking a state appeals court to review it.

May 2026

βœ‹ Turned down

Hazle Township supervisors unanimously rejected the land development plan for Project Hazelnut, a 15-building data center campus on about 1,280 acres near Humboldt Industrial Park. More than 200 residents came out against it.

Nov 14, 2025
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

2018–20202021–2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something