πŸ§ͺ Preview: Pennsylvania test version. Other states are being added.
πŸ“£ Report Something
Approved, not built yet

QTS data center campus (Salem 2), Salem Township

Also called: QTS Salem LLC, SNA North LLC, 4-3 Consulting, QTS Salem (QTS Data Centers)

QTS, a Blackstone company, bought about 1,700 acres from 96 Salem Township landowners for over $500 million. It plans 12 data center buildings and would close some local roads. Construction is planned to start in late 2026.

βœ” ConfirmedSourceLast checked: Oct 6, 2026

Where things stand: Township supervisors unanimously approved the final master plan, lot consolidation and road closings in July 2026. State water and stormwater permits are still under DEP review. The new road still needs land development review.

πŸ•’ Latest update (Aug 22, 2026): Developers said construction is planned to begin in late 2026.

πŸ—“οΈ Next meeting of the people who decide: Oct 13, 2026 Β· 6:00 PM
Salem Township Board of Supervisors. We don't know yet if QTS data center campus (Salem 2), Salem Township is on the agenda. Call the office to check before you go.
πŸ“ Berwick Assembly of God Church, 801 E. 5th Street, Berwick (moved there for big crowds). Supervisors' regular meeting Oct. 13 at 6 p.m.; workshop Oct. 27 at 6 p.m.; Planning Commission Oct. 15 at 5:30 p.m. Agenda was 'coming soon' on Oct. 6 - check salemtwp.org.

What we know

  • πŸ“ WhereAbout 1,700 acres bought from 96 landowners; plan closes parts of Market Street, Moskaluk Road and Kiliti Road, Salem Township, Luzerne County
  • 🏒 CompanyQTS Data Centers (entities QTS Salem LLC / SNA North LLC)
  • πŸ›οΈ Owned byBlackstone
  • 🌳 Size1,700 acres
  • πŸ”Œ Where the power comes fromNear the Susquehanna nuclear plant; uses the regional grid
  • πŸ’§ WaterPublic (municipal) water for building needs, per QTS; supplier not confirmed in public records we could open
  • ❄️ CoolingClosed-loop cooling (developer claim)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

πŸ”Ž What we checked

  • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

What happened so far

  • Jan 23, 2026
    Planning Commission voted 3-2 for SNA North LLC's lot consolidation plan, limiting access to parts of Cemetery Road and Market Street.
  • March 2026
    QTS paid 96 landowners more than $500 million for about 1,700 acres.
  • March 18, 2026
    QTS said that once running, its closed-loop buildings would use public water only for normal building needs, like any commercial building.
  • March 26, 2026
    Planning Commission tabled the updated master plan (cut from 18 to 12 buildings).
  • March 26, 2026
    At the township planning commission, residents asked about private wells. Project representatives said the development would not affect well water.
  • May 28, 2026
    Planning Commission recommended conditional approval; supervisors' public hearing set for June 23, 2026.
  • July 2026
    Supervisors voted unanimously to approve the final master plan, combine 180 lots (1,700 acres) and close parts of North Market Street and Moskaluk Road and all of Kiliti Road. QTS will build a new road first.
  • Aug 22, 2026
    Developers said construction is planned to begin in late 2026.

Local votes and rules

πŸ—ΊοΈ Zoning change

After a court voided its earlier votes, the Salem Township Planning Commission voted a third time to recommend a larger data center overlay zone. The zone would help a third data center project move forward. Township supervisors make the final decision.

Sept 2026

πŸ—ΊοΈ Zoning change

Salem Township supervisors scheduled a vote to expand the township's data center overlay zone for the Salem 3 campus, a planned 39-building project on more than 4,000 acres with its own power plant. Residents went to court over meeting notice and limits on public comment.

Aug 26, 2026

βš–οΈ Court case

A Luzerne County judge ruled that the Salem Township Planning Commission broke the state open-meetings law when some people were locked out of a meeting on a data center zoning overlay. Eight residents without a lawyer brought the case. The ruling voided the commission's earlier vote on an overlay for a third data center project, called Salem 3.

Aug 25, 2026

βœ… Approved

The Salem Township Planning Commission recommended conditional approval of a revised master plan for a QTS data center campus. The new plan cuts the project from 18 buildings to 12 but adds 100 acres. It also involves closing parts of three local roads. Supervisors had approved an earlier master plan.

May 2026

🀝 Agreement with the company

Salem Township supervisors approved a Blackstone QTS data center campus planned for about 1,700 acres bought from 96 landowners. The township received a $9 million community benefit agreement to pay for emergency medical services, roads and other infrastructure, and town services.

March 2026
πŸ›°οΈ See it from above

Drag the slider to compare the land before and now.

2018–20202021–2023
Photos: PEMA / PASDA, Pennsylvania aerial photos.

Live near here?

Tell us what you see, hear, or what your bill looks like.

πŸ“£ Report something