Status unclearBig (AI-size): 185 acres

Sugarloaf Township data center (Tomhicken Road)

Also called: LBT Investment Group, Sugarloaf Logistics

A Chicago company planned a six-building data center on 185 acres in Sugarloaf Township, but it has backed out. The landowner and a buyer are still trying in court to change the zoning so a data center could be built.

👥 Reported, not confirmed yetSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Sugarloaf Township.

Where things stand: Status unclear Supervisors rejected the zoning change. The developer, LBT, has backed out, but the landowner and land buyer are still asking Luzerne County Court to allow data centers there.

❓ 2 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (Sept 18, 2026): The Times-Tribune listed the LBT Sugarloaf project (6 buildings, 185 acres) as seeking a zoning change in Luzerne County Court.

What we know

  • 📍 Where185 acres along Tomhicken Road, about 1.5 miles west of Route 93, Sugarloaf Township, Luzerne County
  • 🏢 CompanyLBT Investment Group LLC (withdrew); Sugarloaf Logistics (land buyer)
  • 🌳 Size185 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Will the judge let the land buyer continue the appeal? 🙋 I'll find out ·
  • Who would build a data center there now? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Feb 17, 2026
      Supervisors' meeting drew a large crowd on the plan; supervisors had rejected the zoning amendments.
    • Sept 2026
      In court, attorneys said LBT backed out; a judge is deciding if the land buyer can take over the appeal.
    • Sept 18, 2026
      The Times-Tribune listed the LBT Sugarloaf project (6 buildings, 185 acres) as seeking a zoning change in Luzerne County Court.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Developer backs out of Sugarloaf Twp. data center project · Citizens' Voice · Sept 24, 2026
    2. Data centers as 2025 newsmaker of the year · The Times-Tribune (via Yahoo News) · Dec 28, 2025
    3. 22 regional data center projects and where they stand · The Times-Tribune · Sept 18, 2026
    4. PA Data Center Permit Tracker - all projects list (CSV behind the DEP map) · Pennsylvania DEP · Oct 6, 2026
    5. PA DEP Data Center Permit Tracker (project list CSV) · Pennsylvania DEP · Oct 7, 2026
    6. OpenStreetMap map check · OpenStreetMap contributors · Oct 7, 2026

    See something wrong? Tell us and we'll fix it.