ProposedBig (AI-size): 460 acres

Hollenback Township landowner rezoning for data centers

More than 30 landowners in Hollenback Township asked to rezone 460 acres of rural land so data centers could be built. No developer has been named. The dispute is now in court.

👥 Reported, not confirmed yetSourceLast checked: Oct 6, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Township Supervisors (in some larger townships, the Board of Commissioners) of Hollenback Township.

Where things stand: Proposed 31 landowners want 460 acres rezoned to industrial to allow data centers; the request moved to court in March 2026.

❓ 2 open questions about it: see below.

Last checked Oct 6, 2026.

🕒 Latest update (Sept 18, 2026): The Times-Tribune listed the Hollenback request (11 data centers on 460 acres) with the developer still unknown. About 30 landowners are seeking a zoning change.

What we know

  • 📍 WhereHollenback Township, Luzerne County
  • 🏢 CompanyGroup of 31 property owners (no data center company named)
  • 🌳 Size460 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • Which data center company, if any, is behind the landowners? 🙋 I'll find out ·
  • What has the court decided? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    🔎 What we checked

    • Oct 6, 2026: We checked the Susquehanna River Basin Commission's public list of water applications: there is no water application from this project. As of mid-2026, SRBC said Amazon's Salem Township campus was the only data center it had approved. A data center needs SRBC approval before it runs if it uses up (mostly by evaporation) more than 20,000 gallons a day on a 30-day average, or takes water from its own wells or streams above SRBC limits.

    What happened so far

    • Jan 2026
      Landowners asked to rezone land from open space and farm-residential to industrial for data centers.
    • March 1, 2026
      Hearing was closed over notice disputes; the request moved to court.
    • Sept 18, 2026
      The Times-Tribune listed the Hollenback request (11 data centers on 460 acres) with the developer still unknown. About 30 landowners are seeking a zoning change.
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    2018–20202021–2023
    We only know the town, so this shows the town center, not the exact site. Photos: PEMA / PASDA, Pennsylvania aerial photos.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Rezoning request to move to court in Hollenback Township · Times Leader · March 1, 2026
    2. 22 regional data center projects and where they stand · The Times-Tribune · Sept 18, 2026
    3. Water Use by Data Centers in the Susquehanna River Basin - FAQ · Susquehanna River Basin Commission · 2026
    4. Water Application and Approval Viewer (WAAV) · Susquehanna River Basin Commission · Oct 6, 2026

    See something wrong? Tell us and we'll fix it.