3 data center projects in Jessup Borough
Who decides here: the Borough Council of Jessup Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
In Jessup Borough
DBT-Data Lackawanna One (Jessup)
Jessup, Lackawanna County
39 acres
🕒 Sept 4, 2026: Application filed for a 200,000-square-foot, one-story data center.
Reported in the news, not confirmed yet
Approved, not built yetSunnyside Road data center (Jessup)
Jessup, Lackawanna County
🕒 Sept 25, 2026: News reports said the Sunnyside Road project is 'tied up in litigation' after Council's …
ProposedBreaker Street data center campus (Jessup)
Jessup, Lackawanna County
131 acres
🕒 Sept 25, 2026: News reports said Breaker Street Associates LLC, tied to Catalyst Commercial Development…
Nearby (within 15 miles)
Triboro data center site (Olyphant)
Olyphant, Lackawanna County
471 acres
🕒 Nov 4, 2026: Olyphant cancelled the Nov. 5 special meeting after the borough's lawyer said a neighbor…
Status unclearabout 4 miles awayDBT-Data Lackawanna Two, Three and Four sites (Archbald/Jessup)
Archbald, Lackawanna County
355 acres
🕒 Sept 2026: Reported that DBT holds memorandums with SLIBCO for three more sites.
Reported in the news, not confirmed yet
Stopped or cancelledabout 4 miles awayBlakely data center campus
Blakely, Lackawanna County
209 acres
🕒 Sept 12, 2025: Developers withdrew the zoning change request after the borough declined another public …
Status unclearabout 4 miles awayPNK Group data centers (Valley View Business Park, Archbald)
Archbald, Lackawanna County
89 acres
🕒 July 2026: PNK began a mail and online campaign about two data centers.
Reported in the news, not confirmed yet
Proposedabout 4 miles awayProject Green Mountain (Archbald)
Archbald, Lackawanna County
271 acres
🕒 Nov 12, 2026: At the fifth conditional use hearing, Green Mountain 6 LLC finished presenting its case …
Stopped or cancelledabout 4 miles awayWildcat Ridge data center campus (Archbald)
Archbald, Lackawanna County
574 acres
🕒 Oct 30, 2026: A lawyer for the developer, Cornell Realty Management, sent a legal notice to a county c…
Proposedabout 5 miles awayProject Scott (Archbald I LLC, 18 buildings)
Archbald, Lackawanna County
400 acres
🕒 Sept 18, 2026: The Times-Tribune listed Project Scott as denied by Archbald Council and in court agains…
Jessup Borough Council. We don't know yet if DBT-Data Lackawanna One (Jessup) is on the agenda. Call the office to check before you go.
Local votes and rules
📌 Other · Lackawanna County
Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.
✋ Turned down
Jessup's Zoning Hearing Board unanimously turned down zoning relief for six data centers planned on Breaker Street. The board said the needed power substation would sit in a residential zone, which is not allowed. The developer can appeal in county court.
📜 Data center rules
Jessup Borough Council voted unanimously to tighten its data center rules. Data centers can only go on industrial land south of the Casey Highway and need a public hearing first. The rules also limit height and require noise studies and water-saving cooling.
What you can do
- Get told first.
We'll email you if anything changes in Jessup Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
PPL Electric Utilities Corp. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.
🙋 Open tasks here
- Who was the planned end user?
- How much power and water will it use?
- Will it buy power directly from the gas plant?
- Who is the end user?
- Who is challenging the Sunnyside Road approval in court, and what is the case about?
- How much water will it use?
- What are the plans for DBT's three other sites (Lackawanna Two, Three, Four)?