1 data center project in Blakely Borough
Who decides here: the Borough Council of Blakely Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
Wildcat Ridge data center campus (Archbald)
Archbald, Lackawanna County
574 acres
🕒 Oct 30, 2026: A lawyer for the developer, Cornell Realty Management, sent a legal notice to a county c…
Proposedabout 2 miles awayDickson City Development data center (Bell Mountain)
Dickson City, Lackawanna County
🕒 Sept 18, 2026: The Times-Tribune listed the Bell Mountain project (4 buildings) as denied by the zoning…
Status unclearabout 3 miles awayPNK Group data centers (Valley View Business Park, Archbald)
Archbald, Lackawanna County
89 acres
🕒 July 2026: PNK began a mail and online campaign about two data centers.
Reported in the news, not confirmed yet
Proposedabout 3 miles awayBreaker Street data center campus (Jessup)
Jessup, Lackawanna County
131 acres
🕒 Sept 25, 2026: News reports said Breaker Street Associates LLC, tied to Catalyst Commercial Development…
Status unclearabout 3 miles awayTriboro data center site (Olyphant)
Olyphant, Lackawanna County
471 acres
🕒 Nov 4, 2026: Olyphant cancelled the Nov. 5 special meeting after the borough's lawyer said a neighbor…
Proposedabout 3 miles awayProject Boson (Archbald)
Archbald, Lackawanna County
86 acres
🕒 Dec 2025: Plan merged into one building of about 620,000 square feet ('Project Boson').
Proposedabout 3 miles awayProject Scott (Archbald I LLC, 18 buildings)
Archbald, Lackawanna County
400 acres
🕒 Sept 18, 2026: The Times-Tribune listed Project Scott as denied by Archbald Council and in court agains…
Approved, not built yetabout 3 miles awaySunnyside Road data center (Jessup)
Jessup, Lackawanna County
🕒 Sept 25, 2026: News reports said the Sunnyside Road project is 'tied up in litigation' after Council's …
Local votes and rules
📌 Other · Lackawanna County
Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.
What you can do
- Get told first.
We'll email you if anything changes in Blakely Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Blakely Borough: PPL Electric Utilities Corp. (company) or Borough of Blakely (not available).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.