1 data center project in Blakely Borough
Who decides here: the Borough Council of Blakely Borough votes on zoning. The Lackawanna County Planning Commission usually reviews big projects too.
In Blakely Borough
Nearby (within 15 miles)
Wildcat Ridge data center campus (Archbald)
Archbald, Lackawanna County
574 acres
π Sept 10, 2026: Council refused to step aside (recusal) and closed the hearing record after 9 hearings.
Proposedabout 2 miles awayDickson City Development data center (Bell Mountain)
Dickson City, Lackawanna County
π Sept 18, 2026: The Times-Tribune listed the Bell Mountain project (4 buildings) as denied by the zoningβ¦
Status unclearabout 3 miles awayPNK Group data centers (Valley View Business Park, Archbald)
Archbald, Lackawanna County
89 acres
π July 2026: PNK began a mail and online campaign about two data centers.
Reported in the news, not confirmed yet
Status unclearabout 3 miles awayTriboro data center site (Olyphant)
Olyphant, Lackawanna County
π April 14, 2026: Borough Council declared its zoning invalid for leaving out data centers, giving itself β¦
Proposedabout 3 miles awayProject Boson (Archbald)
Archbald, Lackawanna County
86 acres
π Dec 2025: Plan merged into one building of about 620,000 square feet ('Project Boson').
Approved, not built yetabout 3 miles awaySunnyside Road data center (Jessup)
Jessup, Lackawanna County
π Sept 25, 2026: News reports said the Sunnyside Road project is 'tied up in litigation' after Council's β¦
Local votes and rules
π Other Β· Lackawanna County
Lackawanna County commissioners voted unanimously to hire EmPower Analytics Group for $165,000. Over 90 days the firm will study the pollution and health effects of more than a dozen proposed data center campuses and power plants in the county.
What you can do
- Get told first.
We'll email you if anything changes in Blakely Borough. - Go to borough meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Depending on where you live in Blakely Borough: PPL Electric Utilities Corp. (company) or Borough of Blakely (not available).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Pennsylvania.