1 data center project in Weathersfield Township
Who decides here: the Township Trustees of Weathersfield Township votes on zoning. Many Ohio townships have their own zoning. Where a township has none, the county decides.
In Weathersfield Township
Nearby (within 15 miles)
Possible data center at former McDonald Steel site
McDonald, Trumbull County
350 acres
π Sept 15, 2026: Oppidan held a public question-and-answer meeting at McDonald High School.
Proposedabout 5 miles awayBristolville 25 data center campus (Lordstown)
Lordstown, Trumbull County
133 acres
π June 15, 2026: Public hearing set on extending the pause by another 180 days.
Being builtabout 6 miles awaySoftBank Stargate data center at former GM Lordstown plant
Lordstown, Trumbull County
for OpenAI (Stargate project with SoftBank and Oracle)
π Oct 2025: Crews began clearing the old parking lot in front of the plant for the data center.
Stopped or cancelledabout 12 miles awayCrane Data Centers 'Project Milo' (Hubbard)
Hubbard, Trumbull County
π July 6, 2026: Residents turned in a petition to put a permanent data center ban on the November ballot.
Local votes and rules
βΈοΈ Pause on new data centers
Township trustees passed a six-month pause (moratorium) on new data centers. It is set to end in October 2026.
What you can do
- Get told first.
We'll email you if anything changes in Weathersfield Township. - Go to township meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
π Get told first
β‘ Your electric company
Ohio Edison Co. (company).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in Ohio.
π Open tasks here
- Will Bitdeer ask Weathersfield for a zoning variance after the pause ends?
- How much water would the site use? A council member cited 500,000 gallons a day; the company has not confirmed a number publicly.