Being builtBig (AI-size): Described as an AI or hyperscale project in the sources

SoftBank Stargate data center at former GM Lordstown plant

Also called: Stargate Lordstown, Foxconn Lordstown plant

SoftBank bought the old GM car plant in Lordstown and is building an AI data center on part of the site for the Stargate project with OpenAI and Oracle. Foxconn still makes data center equipment inside the plant. The companies said Lordstown and a Texas site together could grow to 1.5 gigawatts.

✔ ConfirmedSourceLast checked: Oct 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the Village Board of Lordstown Village.

Where things stand: Being built SoftBank broke ground in 2025 and said it would open in 2026.

❓ 3 open questions about it: see below.

Last checked Oct 8, 2026.

🕒 Latest update (Oct 2025): Crews began clearing the old parking lot in front of the plant for the data center.

What we know

  • 📍 WhereFormer GM / Foxconn plant, northwest corner near Hallock Young Road, Lordstown, Trumbull County
  • 🏢 CompanySoftBank Group
  • 🏛️ Owned bySoftBank Group
  • 👤 Built forOpenAI (Stargate project with SoftBank and Oracle)

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

  • How many megawatts will the Lordstown building use? 🙋 I'll find out ·
  • Is the data center open yet? 🙋 I'll find out ·
  • Where will the power and water come from? 🙋 I'll find out ·

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • Aug 2025
      Foxconn sold the Lordstown plant to SoftBank for $375 million.
    • Sept 23, 2025
      OpenAI, Oracle and SoftBank named Lordstown as a Stargate site, set to open in 2026.
    • Oct 2025
      Crews began clearing the old parking lot in front of the plant for the data center.

    Local votes and rules

    ⚖️ Court case

    The Ohio Supreme Court ruled unanimously that Lordstown does not have to review a data center site plan from Bristolville 25 Developer while the village pause on data centers is in place.

    Oct 20, 2026

    ⏸️ Pause on new data centers

    Village council passed a 180-day pause (moratorium) on data center applications in January 2026, then extended it for another 180 days in mid-2026. A data center developer is challenging it at the Ohio Supreme Court. It is set to end in January 2027.

    Jan 5, 2026

    ⚖️ Court case

    Developer Bristolville 25 sued the village at the Ohio Supreme Court after the village would not review its plan for a data center campus on 133 acres near the old GM plant. Council passed a ban in November 2025, repealed it, and then passed a pause (moratorium) instead. The case is ongoing.

    Nov 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something

    Where this comes from

    1. Lordstown Data Center to Be Operational Next Year · The Business Journal · Sept 23, 2025
    2. Preparation Work Begins on Lordstown Data Center · The Business Journal · Oct 28, 2025
    3. OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites · OpenAI · Sept 23, 2025
    4. U.S. Census Geocoder result for 2300 Hallock Young Rd, Warren, OH 44481 · U.S. Census Bureau · Oct 7, 2026
    5. Data center to occupy small part of Lordstown AI hub · WFMJ · 2025
    6. Hallock Young Road, Lordstown · OpenStreetMap Nominatim · Oct 8, 2026
    7. USGS satellite image of the site · USGS The National Map · Oct 8, 2026

    See something wrong? Tell us and we'll fix it.