SoftBank Stargate data center at former GM Lordstown plant
Also called: Stargate Lordstown, Foxconn Lordstown plant
SoftBank bought the old GM car plant in Lordstown and is building an AI data center on part of the site for the Stargate project with OpenAI and Oracle. Foxconn still makes data center equipment inside the plant. The companies said Lordstown and a Texas site together could grow to 1.5 gigawatts.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Village Board of Lordstown Village.
Where things stand: Being built SoftBank broke ground in 2025 and said it would open in 2026.
❓ 3 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (Oct 2025): Crews began clearing the old parking lot in front of the plant for the data center.
What we know
- 📍 WhereFormer GM / Foxconn plant, northwest corner near Hallock Young Road, Lordstown, Trumbull County
- 🏢 CompanySoftBank Group
- 🏛️ Owned bySoftBank Group
- 👤 Built forOpenAI (Stargate project with SoftBank and Oracle)
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- How many megawatts will the Lordstown building use? 🙋 I'll find out ·
- Is the data center open yet? 🙋 I'll find out ·
- Where will the power and water come from? 🙋 I'll find out ·
What happened so far
- Aug 2025Foxconn sold the Lordstown plant to SoftBank for $375 million.
- Sept 23, 2025OpenAI, Oracle and SoftBank named Lordstown as a Stargate site, set to open in 2026.
- Oct 2025Crews began clearing the old parking lot in front of the plant for the data center.
Local votes and rules
⚖️ Court case
The Ohio Supreme Court ruled unanimously that Lordstown does not have to review a data center site plan from Bristolville 25 Developer while the village pause on data centers is in place.
⏸️ Pause on new data centers
Village council passed a 180-day pause (moratorium) on data center applications in January 2026, then extended it for another 180 days in mid-2026. A data center developer is challenging it at the Ohio Supreme Court. It is set to end in January 2027.
⚖️ Court case
Developer Bristolville 25 sued the village at the Ohio Supreme Court after the village would not review its plan for a data center campus on 133 acres near the old GM plant. Council passed a ban in November 2025, repealed it, and then passed a pause (moratorium) instead. The case is ongoing.
Drag the slider to compare the land before and now.
Where this comes from
- Lordstown Data Center to Be Operational Next Year · The Business Journal · Sept 23, 2025
- Preparation Work Begins on Lordstown Data Center · The Business Journal · Oct 28, 2025
- OpenAI, Oracle, and SoftBank expand Stargate with five new AI data center sites · OpenAI · Sept 23, 2025
- U.S. Census Geocoder result for 2300 Hallock Young Rd, Warren, OH 44481 · U.S. Census Bureau · Oct 7, 2026
- Data center to occupy small part of Lordstown AI hub · WFMJ · 2025
- Hallock Young Road, Lordstown · OpenStreetMap Nominatim · Oct 8, 2026
- USGS satellite image of the site · USGS The National Map · Oct 8, 2026