5 data center projects we know about. 36 townships, cities and villages.

Built & runningBeing builtApproved, not built yetProposedStopped or cancelled

Local votes and rules

🗳️ Public vote · Hubbard

Voters will decide whether to fully ban data centers in the city. The city was negotiating with a possible data center developer.

Nov 3, 2026Source

⏸️ Pause on new data centers · McDonald

Village council passed a one-year pause (moratorium) on new data centers. It is set to end in September 2027.

Sept 2026Source

⏸️ Pause on new data centers · Newton Falls

Village council passed a one-year pause (moratorium) on new data centers. It is set to end in September 2027.

Sept 2026Source

⏸️ Pause on new data centers · Warren

City council unanimously passed a one-year pause (moratorium) on data centers larger than 1,000 square feet. It is set to end in September 2027.

Sept 2026Source

⏸️ Pause on new data centers · Vienna

Township trustees extended their pause (moratorium) on data centers by 60 days. It is set to end in October 2026.

Aug 2026Source

⏸️ Pause on new data centers · Girard

City council passed a one-year pause (moratorium) on new data centers. It is set to end in July 2027.

July 2026Source

⏸️ Pause on new data centers · Braceville

Township trustees passed a six-month pause (moratorium) on new data centers. It is set to end in December 2026.

June 2026Source

⏸️ Pause on new data centers · Cortland

City council passed a one-year pause (moratorium) on new data centers. It is set to end in June 2027.

June 2026Source

⏸️ Pause on new data centers · Howland

Township trustees passed a six-month pause (moratorium) on new data centers. It is set to end in December 2026.

June 2026Source

⏸️ Pause on new data centers · Hubbard

City council passed a one-year pause (moratorium) on new data centers. It is set to end in June 2027.

June 2026Source

⏸️ Pause on new data centers · Bazetta

Township trustees passed a 180-day (about six months) pause (moratorium) on new data centers. It is set to end in November 2026.

May 2026Source

⏸️ Pause on new data centers · Niles

City council passed a six-month pause (moratorium) on new data centers. It is set to end in November 2026.

May 2026Source

⏸️ Pause on new data centers · Weathersfield

Township trustees passed a six-month pause (moratorium) on new data centers. It is set to end in October 2026.

April 2026Source

⏸️ Pause on new data centers · Hubbard

Township trustees passed a one-year pause (moratorium) on new data centers. It is set to end in February 2027.

Feb 2026Source

⏸️ Pause on new data centers · Lordstown

Village council passed a 180-day pause (moratorium) on data center applications in January 2026, then extended it for another 180 days in mid-2026. A data center developer is challenging it at the Ohio Supreme Court. It is set to end in January 2027.

Jan 5, 2026Source

⚖️ Court case · Lordstown

Developer Bristolville 25 sued the village at the Ohio Supreme Court after the village would not review its plan for a data center campus on 133 acres near the old GM plant. Council passed a ban in November 2025, repealed it, and then passed a pause (moratorium) instead. The case is ongoing.

Nov 2025Source