Bristolville 25 data center campus (Lordstown)
Also called: Bristolville 25 Lordstown Data Center
A company called Bristolville 25 wants to build a $3.6 billion AI data center on 133 acres along Route 45 in Lordstown. The village paused data center applications, and the company sued to force a review of its plan. It offered $10.8 million for village water upgrades.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the Village Board of Lordstown Village.
Where things stand: Proposed The Ohio Supreme Court ruled on Oct. 20, 2026 that the village does not have to review the site plan while its data center pause is in place. The pause runs to about January 2027.
- Oct 20, 2026: Lordstown, Trumbull County: lawsuit decided Source
❓ 2 open questions about it: see below.
Last checked Oct 26, 2026.
🕒 Latest update (Oct 20, 2026): The Ohio Supreme Court ruled unanimously against the developer. It said the village has no duty to review the site plan while the pause is in place.
What we know
- 📍 WhereAlong State Route 45, near the former GM plant. About 99 acres in Trumbull County and 37 acres in Mahoning County., Lordstown, Trumbull County
- 🏢 CompanyBristolville 25 Developer LLC
- 🌳 Size133 acres
- 💵 Cost$3.6 billion
- 👷 Jobs promised120
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Who would use the data center, and how much power and water would it need? 🙋 I'll find out ·
- Will the developer try again after the village pause ends in January 2027? 🙋 I'll find out ·
What happened so far
- May 2024Village council rezoned the land from highway business to industrial.
- Oct 20, 2025Developer sent a site plan to the village for review.
- Nov 2025Developer sued the village at the Ohio Supreme Court, saying its plan was not reviewed.
- Nov 3, 2025Village council voted to ban data centers.
- Dec 2025Council repealed the ban.
- Jan 5, 2026Council passed a 180-day pause (moratorium) on data center applications.
- June 15, 2026Public hearing set on extending the pause by another 180 days.
- July 6, 2026Village council extended the pause on data center applications by another 180 days, to about January 2027.
- Oct 20, 2026The Ohio Supreme Court ruled unanimously against the developer. It said the village has no duty to review the site plan while the pause is in place.
Local votes and rules
⚖️ Court case
The Ohio Supreme Court ruled unanimously that Lordstown does not have to review a data center site plan from Bristolville 25 Developer while the village pause on data centers is in place.
⏸️ Pause on new data centers
Village council passed a 180-day pause (moratorium) on data center applications in January 2026, then extended it for another 180 days in mid-2026. A data center developer is challenging it at the Ohio Supreme Court. It is set to end in January 2027.
⚖️ Court case
Developer Bristolville 25 sued the village at the Ohio Supreme Court after the village would not review its plan for a data center campus on 133 acres near the old GM plant. Council passed a ban in November 2025, repealed it, and then passed a pause (moratorium) instead. The case is ongoing.
Drag the slider to compare the land before and now.
Where this comes from
- $3.6 billion AI data center looking to locate in Lordstown · WFMJ · Oct 2025
- AI Data Center plans in Lordstown at risk pending ban from council · WFMJ · Oct 2025
- Lordstown continues navigating data center lawsuit · Spectrum News 1 · Feb 24, 2026
- Lordstown looks to extend moratorium on data centers · Tribune Chronicle · May 2026
- Ohio Supreme Court asked to halt Lordstown data center freeze · WFMJ · May 2026
- State ex rel. Bristolville 25 Developer LLC v. Lordstown, 2026-Ohio-4073 · Court News Ohio (Supreme Court of Ohio) · Oct 20, 2026
- Ohio Supreme Court: Village with data center moratorium won't have to consider site plan · Ohio Capital Journal · Oct 26, 2026