Mecklenburg County
5 data center projects we know about. 9 towns, cities and unincorporated areas.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Projects
PowerHouse Charlotte data center campus (University City)
Charlotte, Mecklenburg County
122 acres
🕒 June 8, 2026: Charlotte paused new data center projects; this one was already in development and may c…
Stopped or cancelledProject Accelerate data center (Matthews, withdrawn)
Matthews, Mecklenburg County
123 acres
🕒 Oct 7, 2025: The developers withdrew the rezoning request after strong opposition.
Approved, not built yetDigital Realty data center campus on Moores Chapel Road
Charlotte, Mecklenburg County
156 acres
🕒 Aug 2026: Duke Energy plans for a new substation for the site were reported.
ProposedDigital Realty data center at 725 E. Trade St.
Charlotte, Mecklenburg County
🕒 June 8, 2026: Charlotte paused new data center projects for 150 days; this project was already in the …
Reported in the news, not confirmed yet
ProposedAmerican Tower data center near Reedy Creek Nature Preserve
Charlotte, Mecklenburg County
58 acres
🕒 July 2026: The hearing was delayed from June to at least November 2026.
Local votes and rules
⏸️ Pause on new data centers · Charlotte
City Council voted unanimously to extend its pause on new data center permits by about 11 months, to Oct. 18, 2027. The first pause was set to end Nov. 5, 2026. Permits already given are not affected. Council members said they hope state lawmakers pass data center rules early next session.
⏸️ Pause on new data centers · Charlotte
City Council held a public hearing on making the data center pause last up to 11 months longer. The current pause ends Nov. 5, 2026. Most reports say the vote is set for Oct. 26.
⏸️ Pause on new data centers · Charlotte
Charlotte City Council unanimously paused new data center applications for 150 days, until Nov. 5, 2026 or until new rules pass. A consultant and city team will study effects and propose rules. Projects already approved or in permitting can continue.
🗺️ Zoning change · Charlotte
Charlotte City Council approved rezoning 156 acres off Moores Chapel Road for a Digital Realty data center campus of up to about 3 million square feet. Because it was approved first, the 2026 city pause does not apply to it.
Find your town
In North Carolina, cities and towns decide inside their limits. Outside them, the county decides.