1 data center project in Matthews Town
Who decides here: the Town Council of Matthews Town votes on zoning. The Mecklenburg County may review big projects too.
Big = 100+ megawatts or 100+ acres, or it's described as an AI project. Projects of unknown size always stay on.
Nearby (within 15 miles)
American Tower data center near Reedy Creek Nature Preserve
Charlotte, Mecklenburg County
58 acres
🕒 July 2026: The hearing was delayed from June to at least November 2026.
Proposedabout 10 miles awayDigital Realty data center at 725 E. Trade St.
Charlotte, Mecklenburg County
🕒 June 8, 2026: Charlotte paused new data center projects for 150 days; this project was already in the …
Reported in the news, not confirmed yet
Proposedabout 13 miles awayPowerHouse Charlotte data center campus (University City)
Charlotte, Mecklenburg County
122 acres
🕒 June 8, 2026: Charlotte paused new data center projects; this one was already in development and may c…
What you can do
- Get told first.
We'll email you if anything changes in Matthews Town. - Go to council meetings.
Anyone can speak. Big projects usually need a public hearing. - Ask questions in writing.
Use our checklist.
🔔 Get told first
⚡ Your electric company
Depending on where you live in Matthews Town: Duke Energy Carolinas, LLC (company) or Union Electric Membership Corp. (co-op (owned by its members)).
Big data centers need a lot of power. Who pays for new power lines depends on state rules. See the rules in North Carolina.
🙋 Open tasks here
- Could the developers bring the plan back in a new form?
- Where exactly is the site? A parcel number, address or agenda link helps.