PowerHouse Charlotte data center campus (University City)
Also called: PowerHouse Charlotte
PowerHouse and Town Lane bought 122 acres in University City for a five-building data center campus with 300 megawatts of power, maybe 500 later. It was already in the works before Charlotte's pause on new data centers.
What happens next?
🗓️ No meeting or deadline known yet.
Zoning here is usually decided by the City Council of Charlotte City.
Where things stand: Proposed Land bought in 2024. In development before Charlotte's June 2026 pause, so it may continue.
❓ 3 open questions about it: see below.
Last checked Oct 8, 2026.
🕒 Latest update (June 8, 2026): Charlotte paused new data center projects; this one was already in development and may continue.
What we know
- 📍 Where10800-11220 University City Boulevard, northeast Charlotte, Charlotte, Mecklenburg County
- 🏢 CompanyPowerHouse Data Centers and Town Lane
- 🏛️ Owned byAmerican Real Estate Partners (AREP)
- 🌳 Size122 acres
- ⚡ Power it needs300 megawatts (about as much as 240,000 homes)
- 🔌 Where the power comes fromDuke Energy; an existing substation next door plus a planned new substation on the site.
❓ Still unanswered
Nobody has answered these in public yet. Can you help find out?
- Which company will use the data centers? 🙋 I'll find out ·
- How much water will it use? 🙋 I'll find out ·
- Has construction started? 🙋 I'll find out ·
🔎 What we checked
- Oct 8, 2026: We checked the site location: county tax records show Charlotte Data Center Campus LLC bought about 123 acres on University City Boulevard in August 2024. The pin is the centre of that land.
What happened so far
- Sept 2024PowerHouse and Town Lane bought 122 acres for a planned 300 MW, five-building campus.
- June 8, 2026Charlotte paused new data center projects; this one was already in development and may continue.
Local votes and rules
⏸️ Pause on new data centers
City Council voted unanimously to extend its pause on new data center permits by about 11 months, to Oct. 18, 2027. The first pause was set to end Nov. 5, 2026. Permits already given are not affected. Council members said they hope state lawmakers pass data center rules early next session.
⏸️ Pause on new data centers
City Council held a public hearing on making the data center pause last up to 11 months longer. The current pause ends Nov. 5, 2026. Most reports say the vote is set for Oct. 26.
⏸️ Pause on new data centers
Charlotte City Council unanimously paused new data center applications for 150 days, until Nov. 5, 2026 or until new rules pass. A consultant and city team will study effects and propose rules. Projects already approved or in permitting can continue.
🗺️ Zoning change
Charlotte City Council approved rezoning 156 acres off Moores Chapel Road for a Digital Realty data center campus of up to about 3 million square feet. Because it was approved first, the 2026 city pause does not apply to it.
Drag the slider to compare the land before and now.
Where this comes from
- Town Lane, PowerHouse Data Centers JV acquire future data center land site in Charlotte, N.C. · IREI · Sept 6, 2024
- Town Lane and PowerHouse Data Centers joint venture acquires future data center land site in Charlotte, NC · Simpson Thacher · Sept 5, 2024
- What Charlotte wants to learn during its 150-day moratorium on new data centers · Bisnow · July 22, 2026
- Parcels 05113202, 05142102, 05142111 at 10800-11220 University City Blvd owned by Charlotte Data Center Campus LLC (about 123 acres, bought Aug 2024) · NC OneMap statewide parcels (county tax records) · Oct 8, 2026
- PowerHouse Charlotte (10800 University City Blvd) · Data Center Map · 2026