American Tower data center near Reedy Creek Nature Preserve

American Tower wants to rezone 58 acres in east Charlotte for offices, telecom and a small data center of about 40,000 square feet on 10 acres. Thousands of neighbors signed a petition against it because the site borders homes and a nature preserve.

✔ ConfirmedSourceLast checked: Oct 7, 2026

What happens next?

🗓️ No meeting or deadline known yet.

Zoning here is usually decided by the City Council of Charlotte City.

Where things stand: Proposed Rezoning not yet decided. The public hearing was pushed back to at least November 2026.

❓ 2 open questions about it: see below.

Last checked Oct 7, 2026.

🕒 Latest update (July 2026): The hearing was delayed from June to at least November 2026.

What we know

  • 📍 Where8036 Hood Road, east Charlotte, next to Reedy Creek Nature Preserve, Charlotte, Mecklenburg County
  • 🏢 CompanyAmerican Tower
  • 🌳 Size58 acres

❓ Still unanswered

Nobody has answered these in public yet. Can you help find out?

✉️ Ask for it in writing

Copy this letter, fill in the parts in [brackets], and send it by email or mail.

    This is a template, not legal advice.

    What happened so far

    • April 2026
      American Tower asked to delay the rezoning hearing after strong opposition.
    • July 2026
      The hearing was delayed from June to at least November 2026.

    Local votes and rules

    ⏸️ Pause on new data centers

    City Council voted unanimously to extend its pause on new data center permits by about 11 months, to Oct. 18, 2027. The first pause was set to end Nov. 5, 2026. Permits already given are not affected. Council members said they hope state lawmakers pass data center rules early next session.

    Oct 26, 2026

    ⏸️ Pause on new data centers

    City Council held a public hearing on making the data center pause last up to 11 months longer. The current pause ends Nov. 5, 2026. Most reports say the vote is set for Oct. 26.

    Oct 12, 2026

    ⏸️ Pause on new data centers

    Charlotte City Council unanimously paused new data center applications for 150 days, until Nov. 5, 2026 or until new rules pass. A consultant and city team will study effects and propose rules. Projects already approved or in permitting can continue.

    June 8, 2026

    🗺️ Zoning change

    Charlotte City Council approved rezoning 156 acres off Moores Chapel Road for a Digital Realty data center campus of up to about 3 million square feet. Because it was approved first, the 2026 city pause does not apply to it.

    May 2025
    🛰️ See it from above

    Drag the slider to compare the land before and now.

    20182025
    Photos: Sentinel-2 cloudless by EOX IT Services GmbH (contains modified Copernicus Sentinel data), CC BY-NC-SA 4.0.

    Live near here?

    Tell us what you see, hear, or what your bill looks like.

    📣 Report something